§ 03 REPORTS / AI / 2026-10-27

How the AI Supply Chain Works

FILED UNDER AI § 2026-10-27

Who builds, who pays, who lends, and what can break it, explained from the ground up. | October 2026

tl;dr


Contents

  1. The game in one page
  2. What the product is
  3. The five layers and their clocks
  4. The chain from sand to socket
  5. Demand: who pays for the hours
  6. Financing: how the money shows up
  7. The players
  8. Who sets the date, what regulation does, what a ban would do
  9. What earlier buildouts teach
  10. How to read a new headline
  11. The conjecture, and what would break it
  12. Data sources and methodology

The game in one page

This report borrows its premise. In an essay on NVIDIA's blog on 10 March 2026, Jensen Huang, who runs NVIDIA, the company that designs most AI chips, described AI as a five layer cake: energy, chips, infrastructure, models and applications, in that order. "At the top are applications, where economic value is created," he wrote, and "every successful application pulls on every layer beneath it, all the way down to the power plant that keeps it alive." An AI site, a building full of specialized computers on a large electricity supply, is where the lower three layers meet.

Here, layer one is power: a grid connection or a power plant next door. Layer two is the chips, with the factories and memory makers behind them. Layer three is the building, its cooling, and the clouds and neoclouds (companies that mainly rent out AI chips, such as CoreWeave) that run the halls. Layer four is the labs, companies whose main product is an AI model. Layer five is the businesses and people paying for answers.

The buyer, whoever signs to pay for the hours, sits at layer four or five. Without models the three layers below earn nothing. The largest signatures here come from labs: Anthropic's compute promises of roughly $640 billion (Anthropic S-1) and OpenAI's $250 billion Azure contract (Microsoft 10-Q, September 2025). A lab can keep paying only if layer five grows into those promises, and section 5 shows that loop does not yet close.

The cake gives the layers and their order, from the company that builds layer two and sells into layer three, so it is a seller's map; this report reads it from the lender's side. What it does not say, and this report adds, is that each layer runs on its own clock, who pays whom and when, that one gigawatt has three prices, and that the money follows the signature. Power and buildings take years. Chips take months. NVIDIA is paid shortly after delivery. The buyer starts paying only after the site is running.

That gap between paying for the chips and getting paid by the buyer is where the money question lives. Someone has to fund the wait. A lender is a bank, a fund or a bond buyer who hands over cash now in exchange for a promise to be repaid with interest later. The company that can borrow is the company that already has a promise of payment from a customer, or other businesses that can pay the bill. A bare hope that customers will show up later supports only the owner's own money. A shorter or weaker promise gets funded, but at a higher rate, for a smaller loan, with more cushion and a parent guarantee, as section 6 shows.

The scarce input sets the date. Right now that input is power, not chips. NVIDIA still ships on its own date, because buyers are afraid to lose their place in line. Everyone else pays to keep up.

The report walks the layers in Huang's order: what the product is, each layer's clock, the chip chain from sand to socket, who at layers four and five pays for the hours, how the money shows up, then regulation, a ban and earlier buildouts.

By the end, a reader should be able to take any AI infrastructure headline and ask four questions. Which price is this: the chip seller's sales into a site, the owner's rent, or the return a builder needs? Who has signed to pay, and can they leave? Is the power connected? Does the guarantee start now, or only after a building is finished and a tenant then misses a payment?

What the product is

A model is a very large list of numbers plus a recipe

An AI model is a very large list of numbers plus a fixed recipe for combining them. You feed it text. The recipe multiplies and adds the text against the numbers, and out comes a guess at the next small piece of text. Repeat the guess a few hundred times and you get an answer.

Each number in the list is called a parameter, or a weight. The two words mean the same thing. When a lab "releases the weights", it publishes the list so anyone can run the model on their own machines.

The small piece of text is called a token. A token is often part of a word; one English word is about one to two tokens (a16z, November 2024). Labs price everything per million tokens. Input tokens are what you send in. Output tokens are what the model writes back, and output tokens cost about five times more than input tokens on the frontier price lists checked for this report in late October 2026 (GPT-5's 2025 list was eight times) (OpenAI, Anthropic, Google).

A concrete model makes the scale clear. Moonshot's Kimi K3 holds 2.8 trillion numbers, but only about 104 billion of them do work on any one token, because the list is split into smaller sub networks and a router picks a few for each token (Kimi K3 model card). You need room for the whole list, which is memory. Each answer costs only the part you use, which is compute.

Training sets the numbers once, inference runs every day

Training is the one time job of setting the numbers. The model reads a huge pile of text, guesses the next token, checks the real answer, and nudges every number slightly toward the right guess, trillions of times. A 2020 paper from OpenAI gives the rule of thumb: producing one token costs about 2 operations per active parameter, and training costs about 6 operations per parameter per training token, because each training step runs forward and then backward to work out the nudges (Kaplan et al., 2020). Epoch AI estimates OpenAI's GPT-6 Astra took about 9.4 × 10^26 operations to train, on about 100,000 NVIDIA GB200 chips drawing about 233 megawatts, with the label "likely", meaning within about ten times (Epoch AI models database).

Inference is using the finished model: every chat answer, every coding agent step, every API call. It is paid by the token and runs every day for as long as the model is sold. Training is a fixed cost per model. Inference grows with every customer.

No company publishes a full split between the two. Deloitte forecast that inference "will make up two-thirds of AI compute by 2026" (Deloitte, 18 November 2025). The International Energy Agency wrote in April 2026 that the balance of AI energy use "has already shifted decisively from training to inference" and gave no number (IEA, Key Questions on Energy and AI). Epoch AI, working from reported investor documents, estimated that OpenAI spent about $5 billion on research and training compute and about $1.8 billion on inference compute in 2024 (Epoch AI, 10 October 2025). So at one lab in 2024, training and research were the larger bill, while the forecast for the market as a whole is that inference now dominates. Both are estimates.

Why these machines

Producing one token is billions of small multiplications that do not depend on each other, so they can all be done at the same moment. The main chip in a laptop, a CPU, has a handful of strong cores built to do a few tasks one after another very quickly. A GPU has thousands of simpler cores that do the same small sum on many numbers at once. Any chip built for this kind of bulk math is called an accelerator. NVIDIA's GPUs are the main example; Google's TPU and Amazon's Trainium are accelerators built for one company.

A fast chip next to slow memory spends most of its time waiting, because to write each token the chip must read the active weights out of memory. So AI chips sit beside a special kind of memory called HBM, high bandwidth memory: memory chips stacked on top of each other and placed in the same package as the GPU, so numbers move very fast. A Rubin GPU, the 2026 generation, has 288 gigabytes of it moving 19.2 terabytes a second (NVIDIA Vera Rubin NVL72 page). Only three companies make HBM: SK hynix, Samsung and Micron (NVIDIA 10-K, fiscal 2026). The IEA wrote in April 2026 that a shortage of it "has developed over the past six months and is anticipated to persist through at least the end of 2027" (IEA).

NVIDIA no longer sells the single chip as its main unit. It sells the rack, a steel cabinet about the size of a tall refrigerator holding chips, network switches, power supplies and liquid cooling pipes. The GB200 NVL72 rack holds 72 Blackwell GPUs and 36 Grace CPUs wired together so they act as one big GPU (NVIDIA GB200 NVL72 page), and NVIDIA's user guide says "the rack power consumption is approximately 120kW" (NVIDIA DGX GB200 user guide). NVIDIA does not publish rack prices; analyst and press figures put a GB200 NVL72 at about $3 million (Wing VC, August 2026). The next rack, Vera Rubin NVL72, holds 72 Rubin GPUs; SemiAnalysis estimates 180 to 220 kilowatts per rack (SemiAnalysis, 25 February 2026), and Morgan Stanley's reported price estimate is about $7.8 million, seen only through an article (MarketScale, July 2026).

Watts, kilowatts, megawatts, gigawatts

A watt is a rate of using electricity. A kilowatt is 1,000 watts, about what a space heater draws. A megawatt is 1,000 kilowatts. A gigawatt is 1,000 megawatts, roughly the output of one large nuclear reactor. A watt hour is the energy used by running one watt for one hour, and a kilowatt hour is a thousand of those.

The US Energy Information Administration says the average American home used 865 kilowatt hours a month in 2024 (EIA, 12 May 2025). The arithmetic for one gigawatt goes like this. One gigawatt running all year uses 1,000,000 kilowatts × 8,760 hours = 8,760,000,000 kilowatt hours. One home uses 865 × 12 = 10,380 kilowatt hours a year. So 8,760,000,000 ÷ 10,380 = about 844,000 homes. A one gigawatt site, running flat out, draws the electricity of about 840,000 average American homes, roughly the homes of a city of two million people.

Data center power is quoted two ways and headlines rarely say which. One is the power the chips draw, called the IT load. The other is the power pulled from the grid, including cooling and losses. The IEA puts the ratio at about 1.1 to 1.2 for the best new sites (IEA), so a "1 gigawatt" campus can mean about 0.8 to 0.9 gigawatts of chips.

How many racks fit in a gigawatt of chip power? At 120 kilowatts a rack, 1,000,000 ÷ 120 = about 8,300 GB200 racks, or 8,300 × 72 = about 600,000 GPUs. At 200 kilowatts a rack, the middle of SemiAnalysis's 180 to 220 kilowatt range, 1,000,000 ÷ 200 = about 5,000 Vera Rubin racks, or about 360,000 GPUs; the range gives 4,500 to 5,600 racks. These are my divisions of the sourced rack figures, and they count chip power, not the grid draw of the whole site.

Those counts let us check a number NVIDIA's executives use. On the earnings call of 26 August 2026, chief financial officer Colette Kress said: "Since Hopper, our revenue opportunity has grown from roughly $18 billion per gigawatt to $25 billion with Blackwell, to $40 billion with Vera Rubin, which now spans Vera CPU, Rubin GPU, NVLink, InfiniBand or Ethernet, and Groq LPU." Jensen Huang repeated the three figures on the same call (NVIDIA Q2 FY2027 call transcript). Multiply the rack price by the rack count: $3 million × 8,300 = about $25 billion, which matches the Blackwell figure. $7.8 million × 5,000 = about $39 billion, which matches the Vera Rubin figure. So NVIDIA's "per gigawatt" number is, roughly, rack price times racks per gigawatt of chip power; NVIDIA does not say whether its gigawatt is chip power or site power, so the match is approximate. NVIDIA calls it a "revenue opportunity", meaning its own sales into a site, and the Rubin figure includes CPUs, networking gear and the Groq chip. It is a different number from what the site's owner earns by renting the site out, which is the subject of section 5.

How the product is sold and what one answer costs

The product is sold two ways. A developer's program sends text to the lab through an API, an interface for other software, and pays per million tokens in and out. Or a person pays a flat monthly subscription to a chat app, such as $20 a month for Claude Pro (Claude pricing), and the lab eats the token cost up to a usage cap.

Here is what one ordinary answer costs at the list prices of 27 October 2026, assuming a 200 token question and a 500 token reply. At GPT-6 Astra's or Claude Fable 5.1's price of $10 per million input tokens and $50 per million output tokens, the question costs 200 ÷ 1,000,000 × $10 = $0.002 and the reply costs 500 ÷ 1,000,000 × $50 = $0.025, so the answer costs about 2.7 cents. At Claude Opus 5.5's $4 and $20, it is about 1.1 cents. At Kimi K3.1 Pro's or Gemini 4 Argon's $2 and $10, it is about 0.5 cents (OpenAI pricing; Anthropic pricing; Google pricing; DataCamp on Kimi K3.1 Pro pricing). Reasoning models write hidden "thinking" tokens before they answer, and those are billed as output tokens. If the same answer carried 5,000 hidden tokens, the output bill at $50 per million becomes 5,500 ÷ 1,000,000 × $50 = $0.275, so the answer costs about 28 cents, ten times the plain version. The 5,000 figure is an illustration, not a measured average.

The electricity in one answer is tiny. Google measured its median Gemini text prompt in May 2025 at 0.24 watt hours, counting the chips, the supporting computers, idle spare machines and building overhead (Google, arXiv 2508.15734). Sam Altman has said about 0.34 watt hours for an average ChatGPT query (Altman, The Gentle Singularity). At the IEA's cheap US industrial price of $60 per megawatt hour, which is $0.06 per kilowatt hour, 0.24 watt hours is 0.00024 kilowatt hours × $0.06 = about $0.000014, about one thousandth of a cent. The chips, the building and the margin are almost all of the token price.

Turn that around. One gigawatt hour is one gigawatt running for one hour, or 1,000,000,000 watt hours. At 0.24 watt hours per answer that is about 4.2 billion simple answers; at 0.34, about 2.9 billion. So a one gigawatt campus could in principle serve billions of simple text answers every hour. The IEA uses this arithmetic to show that simple chat cannot explain the size of planned capacity: ten billion queries a day at a generous 1 watt hour each is about 3.6 terawatt hours a year, under 1 percent of the 485 terawatt hours all data centers used in 2025 (IEA). The rest is training, reasoning, agents, images and video, and enterprise work that no company has broken out.

Two things move in token prices

The price of a fixed level of ability has collapsed. Epoch AI estimates that the cost of reaching a given benchmark score fell about 47 percent per quarter since 2023, which is about 13 times per year, and gives the example that o3 cost about $0.30 per question on a science benchmark in January 2025 while GPT-5.6 Luna reached the same score for $0.0004, a 725 times drop in under 18 months (Epoch AI, 22 September 2026). a16z estimated about 10 times per year in 2024 (a16z).

The list price of the newest, best model has not fallen, and in late 2026 some prices rose. OpenAI's GPT-5 listed at $1.25 in and $10 out in August 2025; GPT-6 Astra lists at $10 and $50 (OpenAI pricing). Google's page says Gemini 4 Argon goes from $2 and $10 to $4 and $20 on 1 December 2026, and two Flash models double on 1 January 2027 (Google pricing). Last year's ability gets very cheap fast. This year's best ability keeps a high price.

That split matters for everything that follows. The figure below puts the two lines on one chart: the falling price of a fixed score and the flat or rising list price of the newest model.

Two token prices move in opposite directionsLog scale, $ per million tokens. Orange: cheapest model that matches GPT-4's March 2023 score on PhD level science questions (Epoch AI). Blue: OpenAI's list price for output tokens of its newest flagship at release.Two token prices move in opposite directionsLog scale, $ per million tokens. Orange: cheapest model that matches GPT-4's March 2023 score on PhD levelscience questions (Epoch AI). Blue: OpenAI's list price for output tokens of its newest flagship at release.$0.1$1$10$1002023202420252026GPT-4, Mar 2023: $37.5 per million tokensClaude 3 Haiku, Mar 2024: $0.5 per million tokensGemini 1.5 Flash, May 2024: $0.13 per million tokensPhi 4, Dec 2024: $0.12 per million tokensgpt-4-0613 (2023-06-13): $60 per million output tokensgpt-4-turbo-2024-04-09 (2024-04-09): $30 per million output tokensgpt-4o-2024-05-13 (2024-05-13): $15 per million output tokensgpt-5 (2025-08-07): $10 per million output tokensgpt-5.2 (2025-12-11): $14 per million output tokensgpt-5.4 (2026-03-05): $15 per million output tokensgpt-5.5 (2026-04-23): $30 per million output tokensgpt-6-astra (2026-09-03): $50 per million output tokensGPT-4 level, Mar 2023: $37.50same level, Dec 2024: $0.12 (Phi 4)GPT-4, Jun 2023: $60 outGPT-6 Astra: $50 outGPT-5: $10 outCheapest model at GPT-4's scoreNewest OpenAI flagship, output priceSources: Epoch AI, LLM inference price trends (12 Mar 2025); OpenAI pricing page, 27 Oct 2026; release dates from Epoch AI.
Figure 8. Two token prices move in opposite directions. The price of a model that matches GPT-4's March 2023 score on PhD level science questions fell from $37.50 to $0.12 per million tokens in 21 months (Epoch AI). The list price of OpenAI's newest flagship fell from GPT-4 to GPT-5 and then rose to $50 per million output tokens for GPT-6 Astra in September 2026. Last year's ability gets cheap fast; this year's best ability keeps a high price. Sources: Epoch AI; OpenAI pricing page.
Table view: Token prices
DateSeriesModel$ per million tokens
2023-03-14fixed abilityGPT-4, Mar 202337.5
2024-03-04fixed abilityClaude 3 Haiku, Mar 20240.5
2024-05-10fixed abilityGemini 1.5 Flash, May 20240.13
2024-12-13fixed abilityPhi 4, Dec 20240.12
2023-06-13newest flagship (output)gpt-4-061360
2024-04-09newest flagship (output)gpt-4-turbo-2024-04-0930
2024-05-13newest flagship (output)gpt-4o-2024-05-1315
2025-08-07newest flagship (output)gpt-510
2025-12-11newest flagship (output)gpt-5.214
2026-03-05newest flagship (output)gpt-5.415
2026-04-23newest flagship (output)gpt-5.530
2026-09-03newest flagship (output)gpt-6-astra50

The five layers and their clocks

Power

Power is layer one, energy in Huang's cake. It means a connection to the electricity grid, or a power plant on the same site. It takes the longest of the five layers.

Some vocabulary. Electricity leaves a power plant on the big wires on tall towers, called transmission, at high voltage, and reaches homes over smaller lines on wooden poles, called distribution. A very large data center connects straight to transmission. The connection point is a substation, a fenced yard of electrical equipment where lines meet and voltage is changed. Inside it sits a transformer, the machine that steps voltage up or down; a large one is a custom built, multi ton unit ordered to a specification. The utility is the company that owns the local wires and sends the bill. The grid operator is a nonprofit that runs the high voltage grid and the wholesale power market for a region and studies whether new plants and new big users can connect safely. ERCOT runs most of Texas. PJM runs 13 states plus Washington DC, including Northern Virginia, the largest data center market in the world. FERC is the federal regulator above grid operators outside Texas; states control retail rates.

The formal application to connect a new power plant or a new big user is an interconnection request, and the list of pending requests is the queue. Being in the queue does not mean a project will be built. Lawrence Berkeley National Laboratory found that of all the generation capacity that asked to connect from 2000 to 2020, only 13 percent was operating by the end of 2025 and 75 percent had withdrawn, and that for plants that came online in 2025 the time from request to operation exceeded five years (APPA summary of LBNL Queued Up 2026). That study measures power plants. For big users, the CRE Finance Council's 2026 primer, citing utility filings and Goldman Sachs's power tracker, lists queue times of 3 to 5 years in Northern Virginia, 5 or more in Silicon Valley, 2 to 3 in Phoenix and Dallas, and 1 to 2 in Columbus (CREFC Data Center E-Primer 2026). One article reports that Dominion Energy's data center customers in Virginia face "an average wait of seven years" (Virginia Mercury, 20 July 2026); that is a single secondary source.

The equipment has its own queue. Wood Mackenzie put large power transformer lead times at about 120 weeks in 2024, up from about 50 in 2021, with the largest units at 80 to 210 weeks (Wood Mackenzie; POWER magazine). 210 weeks is about four years. A gas turbine is the machine inside a gas fired power plant. GE Vernova said in July 2026 it was "taking reservations for 2031 deliveries now" (Utility Dive, 23 July 2026); by 28 October 2026 its gas equipment backlog plus slot reservations had grown from 116 to 122 gigawatts, 64 gigawatts firm and 58 reserved, and it expects at least 130 by year end (GE Vernova Q3 2026 release). Siemens Energy's finance chief said "lead times across the company now run three years or more" (Utility Dive, 10 August 2026).

Texas shows what the queue looks like at scale. ERCOT told the state Senate on 29 July 2026 that it was "tracking approximately 474 GW of Large Loads seeking interconnection, of which ~90% are data centers," as of June 2026 (ERCOT Senate testimony deck). The queue had been about 232 gigawatts at the end of 2025 and about 410 gigawatts in March 2026 (ERCOT board deck, 13 April 2026). The state's record peak demand is 91,089 megawatts, set on 22 July 2026 and unofficial until final settlement (ERCOT peak demand archive). So 474 ÷ 91.1 = 5.2: the requests are more than five times everything Texas has ever drawn at once.

On 3 August 2026 Governor Abbott wrote to the chairman of the Public Utility Commission of Texas and the chief executive of ERCOT that they "must conduct a comprehensive verification and audit of all data centers advancing through ERCOT's interconnection process before any additional data centers are approved to move forward" (Governor's directive letter). This was a directive letter, not a commission order or a law. ERCOT then postponed the classifications it owed under its first batch study of large loads (Utility Dive, 5 August 2026); a law firm note puts the audit's end around 10 December 2026 (White & Case). A second directive on 21 September 2026 paused the state environmental agency's permit approvals for data centers (Beveridge & Diamond).

Most of that list will never be built. The best measure of how much of a queue is real comes from Ohio, where the regulator approved a tariff in July 2025 requiring new data centers to pay for at least 85 percent of the capacity they reserve whether they use it or not (POWER magazine). AEP Ohio had held requests for more than 30,000 megawatts. Once the minimum bill applied, 5,642 megawatts had signed service agreements by February 2026, per secondary reports of AEP's letter to the regulator (New Project Media). That is 5,642 ÷ 30,000 = about 19 percent. Asked to pay for the power, four fifths of the queue went away.

The building

The building is the hall, the cooling, and the electrical gear: walls and roof, electrical rooms, backup generators, cooling plant, fiber connections. It does not include the servers and chips, which the tenant usually buys. The building is the core of layer three, which Huang's essay says "includes land, power delivery, cooling, construction, networking and the systems that orchestrate tens of thousands of processors into one machine," and the clouds and neoclouds that run the halls sit in the same layer. A company that builds such halls and rents space and power to tenants is a colocation landlord. Rent is quoted per kilowatt of chip capacity per month, not per square foot, because power is the scarce thing (CREFC E-Primer). A hyperscaler is one of the giant cloud and internet companies that build their own data centers at huge scale: Microsoft, Google, Amazon, Meta, and, as a cloud seller, Oracle. When a hyperscaler leases a whole building, the lease is usually triple net, meaning the tenant pays base rent plus the building's taxes, insurance, maintenance and utilities. CREFC puts triple net hyperscale rents in primary US markets at $100 to $150 per kilowatt per month for 2025 leases.

The building lasts for decades and rents like a warehouse. CBRE's report on North American data centers for the first half of 2026 says asking rents for blocks of 10 megawatts and up rose 6.7 percent in the half (CBRE, North America Data Center Trends H1 2026). CBRE's public text gives percent changes only. A third party reading of CBRE's charts puts the average at about $165 per kilowatt per month (datacenterscouts.com), so treat that level as a reading, not a CBRE statement. On a full gigawatt it works out to $165 × 1,000,000 kilowatts × 12 months = about $1.98 billion a year. A real contract lands in the same place. Applied Digital leases 400 megawatts in North Dakota to CoreWeave for about $11 billion over roughly 15 years (Applied Digital 8-K, 29 August 2025). That is $11,000,000,000 ÷ 15 years = $733 million a year; ÷ 400,000 kilowatts = $1,833 per kilowatt a year; ÷ 12 = about $153 per kilowatt per month. So a landlord earns about $1 billion to $2 billion a year per gigawatt of shell. This rent is real. It does not pay for the chips.

Finished space is full. CBRE's vacancy rate across the eight primary North American markets was 1.4 percent, a record low, with 7,481 megawatts under construction, 80.4 percent of it already leased before completion, and less than 1,500 megawatts of future capacity unclaimed, "roughly six months of supply" (CBRE press release, 27 August 2026). Space on a slide is not space. Goldman Sachs said in May 2026 that only 50 to 60 percent of planned data center capacity would come online as expected over the next two years, as reported by Utility Dive; the note itself is not public (Utility Dive, 29 September 2026).

The chips

The chips are layer two, the processors Huang describes as built to "transform energy into computation efficiently at massive scale." They are the expensive, short lived part. NVIDIA's revenue "is recognized upon transfer of control of products to customers" and payment "is generally due shortly after delivery" (NVIDIA 10-K, fiscal 2026). So NVIDIA is paid at delivery. Its lead times, the wait from order to delivery, have run "more than 12 months" for some products (same filing). The memory makers behind NVIDIA are now paid partly in advance: Micron reports $32 billion of financial commitments from customers, "the vast majority of which are cash deposits," under contracts that bind the customer to buy set volumes (Micron FQ4 2026 prepared remarks).

A lender will fund the portion of the chip cost that a signed contract will repay before the chips get old. How old is "old" is the depreciation question, and section 5 takes it up; the short version is five to six years on the owners' books, and six years in the one lender's document that states an assumption.

The model

The model is layer four, and it is the product. The three layers below exist to run it; without a model, power, a building and chips earn nothing. A lender cannot seize a model and rent it out the way it can seize a rack. The payoff is whatever the product earns after power, the building and the chips are paid for. This layer is equity, the owner's money, which gets paid last and can be lost entirely.

Its clock is set by training, the one time job of setting a model's numbers (section 2), which is paid for before the model earns anything. Epoch AI estimates OpenAI's GPT-6 Astra was trained on about 100,000 NVIDIA GB200 chips drawing about 233 megawatts, with the label "likely" (Epoch AI models database). Revenue then arrives by the token, through inference, for as long as the model is sold. At Anthropic, the first lab to file audited numbers, revenue went from $386 million in 2024 to $4,585 million in 2025 and $11,555 million in the second quarter of 2026 alone (Anthropic S-1). The next training run is funded by new capital, not by the last model's revenue.

The application

Applications are layer five, where Huang writes that "economic value is created." A signature for hours can come from the three buyers section 5 lists: a hyperscaler building for itself and paying out of ads, cloud, retail and software; a lab renting compute; or enterprises and consumers paying for tokens and subscriptions. Menlo Ventures estimates companies spent $37 billion on generative AI in 2025 (Menlo Ventures, 9 December 2025). A lab's signature is itself backed by layer five. Anthropic's compute promises are paid in the end from what its customers pay, and until then from share sales. Its clock starts last, once the site runs.

Three dates

Put the clocks together and three dates fall out.

  1. Cash leaves when the chips arrive. Someone pays NVIDIA. A serial numbered rack replaces that cash.
  2. The chips can work only after power and cooling are ready.
  3. A customer starts paying when the site is actually running, or when a product sells.

The loan follows the first date. The income follows the third. The months in between are a waiting cost. They are not destroyed profit, but someone carries them.

Borrowing a second time against the same racks does not close the gap. You receive cash. You also take on a new debt of the same size. You still have not sold any compute.

Waiting to accept the chips is the sensible move when the hall is late, and buyers do this; the loan is drawn as the chips are delivered, not years before. The rule gets broken for two reasons. Saying "ship later" can hand your place in line to someone who will take the chips now. And some customer contracts have a date. Google's deal with SpaceX said that if SpaceX failed to deliver the committed chips by 30 September 2026, then after a one month grace period Google could end the agreement or accept fewer chips at a reduced fee (SpaceX free writing prospectus, 5 June 2026).

The figure below lines up the lead times of the lower layers, from a grid connection measured in years to a prefabricated pod measured in days.

Four assets, four clocks: how long each input takes to arriveMonths from order or request to delivery, by input. Power and gear take years; chips take months; a prefab pod takes days, but only once the site has power.Four assets, four clocks: how long each input takes to arriveMonths from order or request to delivery, by input. Power and gear take years; chips take months; a prefabpod takes days, but only once the site has power.01 yr2 yr3 yr4 yr5 yr6 yr7 yrGas turbine delivery (GE Vernova taking reservations for 2031): 48 to 60 months. GE Vernova Q2 2026: reservations for 2031 deliveries; Siemens: lead times three years or moreGas turbine delivery (GE Vernova taking reservations for 2031)Grid connection, large load (Northern Virginia 3 to 5 yrs; Dominion avg about 7): 36 to 84 months. CREFC E-Primer 2026 citing Goldman Power Tracker; Virginia Mercury on DominionGrid connection, large load (Northern Virginia 3 to 5 yrs; Dominion avg about 7)Large power transformer (80 to 210 weeks): 18 to 48 months. Wood Mackenzie 2024 and 2025 surveysLarge power transformer (80 to 210 weeks)Grid connection, large load (Columbus 1 to 2 yrs; Dallas, Phoenix 2 to 3): 12 to 36 months. CREFC E-Primer 2026Grid connection, large load (Columbus 1 to 2 yrs; Dallas, Phoenix 2 to 3)CoreWeave Meta loan: chip draws before amortization (about 15 months): 15 to 15 months. DBRS rating release, 3 Apr 2026CoreWeave Meta loan: chip draws before amortization (about 15 months)NVIDIA chip lead time ("more than 12 months" for some products): 12 to 12 months. NVIDIA 10-K FY2026NVIDIA chip lead time ("more than 12 months" for some products)Rack assembly on site (about six months): 6 to 6 months. NVIDIA DSX POD release, 21 Oct 2026Rack assembly on site (about six months)Prefab pod at a prepared site (as little as 14 days): 0.5 to 0.5 months. NVIDIA DSX POD release, 21 Oct 2026Prefab pod at a prepared site (as little as 14 days)Sources: CREFC E-Primer 2026; Wood Mackenzie; GE Vernova, Siemens via Utility Dive; DBRS; NVIDIA 10-K, 21 Oct 2026 release.
Figure 1. How long each input to an AI site takes to arrive, in months. Grid connections and gas turbines run three to seven years, large transformers up to four, NVIDIA chips about a year, on site rack assembly about six months, and a prefab pod as little as fourteen days once a site already has power and cooling. Sources: CREFC, Wood Mackenzie, GE Vernova and Siemens via Utility Dive, DBRS, NVIDIA.
Table view: Lead times by input
InputLow (months)High (months)Source
Gas turbine delivery (GE Vernova taking reservations for 2031)4860GE Vernova Q2 2026: reservations for 2031 deliveries; Siemens: lead times three years or more
Grid connection, large load (Northern Virginia 3 to 5 yrs; Dominion avg about 7)3684CREFC E-Primer 2026 citing Goldman Power Tracker; Virginia Mercury on Dominion
Large power transformer (80 to 210 weeks)1848Wood Mackenzie 2024 and 2025 surveys
Grid connection, large load (Columbus 1 to 2 yrs; Dallas, Phoenix 2 to 3)1236CREFC E-Primer 2026
CoreWeave Meta loan: chip draws before amortization (about 15 months)1515DBRS rating release, 3 Apr 2026
NVIDIA chip lead time ("more than 12 months" for some products)1212NVIDIA 10-K FY2026
Rack assembly on site (about six months)66NVIDIA DSX POD release, 21 Oct 2026
Prefab pod at a prepared site (as little as 14 days)0.50.5NVIDIA DSX POD release, 21 Oct 2026

What one gigawatt costs to build and to run

Estimates of the full cost of a one gigawatt site, chips included, cluster between about $38 billion and $50 billion. Goldman Sachs uses about $42 billion, roughly 70 percent compute and 30 percent shell, per a secondary writeup of a note that is not public (BigGo Finance, 25 September 2026). Epoch AI's bottom up model gets $37.9 billion for a typical site with GB200 racks: servers $21.2 billion, facility $11.4 billion, network $4.9 billion, with land and utility works under $0.2 billion each (Epoch AI). Huang said at GTC Berlin on 21 October 2026 that "a one gigawatt AI factory costs about $50 billion" (keynote transcript); that is the seller's figure.

Running it costs much less than building it. One gigawatt running all 8,760 hours of a year uses 1,000 megawatts × 8,760 hours = 8,760,000 megawatt hours. At the average industrial electricity price in Texas for January to August 2026, 6.77 cents per kilowatt hour or $67.70 per megawatt hour, that is 8,760,000 × $67.70 = about $593 million a year. At Virginia's $100.70 per megawatt hour it is 8,760,000 × $100.70 = about $882 million (EIA Electric Power Monthly, Table 5.6.B). Set that against $21 billion of servers that will be replaced in five or six years, about $4.2 billion a year of chip cost on a five year life. Electricity is roughly a third to two thirds of the rent on the shell and less than a fifth of the yearly chip cost.

The chain from sand to socket

The supply chain runs from the chip factory to the wall socket. This section walks it in the order a chip is made, with who is paid, when, and how much of each sale they keep. Gross margin is revenue minus the direct cost of making the product, as a share of revenue. A company with a 75 percent gross margin keeps $75 of every $100 it sells before paying for research, sales and overhead. Gross margin shows who in the chain has pricing power. Each company's margin is on its own sales, so the percentages below are not slices of one chip's price and do not add up to 100.

Lithography: ASML

A chip is a small slab of silicon with billions of tiny switches drawn on it. The drawing is done on a wafer, a thin round disk of pure silicon about 30 centimeters across, on which many chips are printed at once and then cut apart. The printing step is lithography: a machine shines light through a pattern onto a wafer coated with a chemical that reacts to light, dozens of times, layer on layer. The smallest patterns need extreme ultraviolet light, and one company, ASML in the Netherlands, makes every machine that does it. ASML's gross margin was 57.5 percent in the third quarter of 2026, and its chief executive said "some customers are expressing an interest in placing orders with us for 2029 and even 2030" and that "our supply as currently planned for both 2027 and 2028 will not fully meet the demand of our customers" (ASML Q3 2026 results). The step furthest from the data center expects to fall short of demand for two years.

Wafer fabrication: TSMC

A fab is a chip factory. A foundry is a company whose fabs make chips designed by other companies. NVIDIA designs; it does not print the wafer. Its 10-K calls this a "fabless" strategy and names TSMC in Taiwan and Samsung as its foundries (NVIDIA 10-K). TSMC also makes AMD's chips, Broadcom's custom chips, Google's TPUs and Amazon's Trainium.

TSMC's gross margin was 66.4 percent in the third quarter of 2026 on revenue of $46.72 billion, up 50.9 percent year on year in Taiwan dollars (TSMC 3Q 2026 release). Its second Arizona fab will start volume production in the third quarter of 2027, and its chief executive said on the call: "Definitely, we have a little bit shortage on the back end" (TSMC Q3 2026 call transcript).

Packaging, memory, substrates, testing, optics

The "back end" is what happens after the chip is cut from the wafer. It has to be mounted on something that connects it to power and to other chips. For an AI chip this step became a bottleneck of its own. TSMC's method, called CoWoS, places the GPU and several stacks of HBM memory side by side on a thin slice of silicon with very fine wiring, which then sits on a substrate. The point is to put the memory millimeters from the processor. NVIDIA's 10-K says simply "We utilize CoWoS technology for semiconductor packaging." In 2024 and 2025 there was not enough CoWoS capacity for all the GPUs TSMC could print, so packaging, not printing, set how many AI chips shipped. TSMC publishes no capacity figure for it; only analyst estimates exist, and they disagree, so this report gives none.

HBM comes from SK hynix, Samsung and Micron. Micron's gross margin was 87.0 percent in its quarter ended 3 September 2026, against 40 percent for the whole of the fiscal year before, and it said it had "completed agreements for the vast majority of our calendar 2027 HBM bit supply with significant price increases year over year" (Micron prepared remarks; Micron 10-K). SK hynix reported an 80 percent operating margin, a stricter measure that comes after research and overhead and is not comparable to the gross margins here, for the third quarter of 2026, said it had signed long-term agreements with 14 major customers, up from around 10 a quarter earlier, and said those agreements cover more than half of its planned production capacity for 2027 and 2028 (SK hynix 3Q26 results, 28 October 2026).

Under the package sits the substrate, a layered board that fans thousands of tiny connections out to the server board. Every packaged chip is then run through test machines. Between racks, chips talk to each other over light in glass fiber, and the parts that convert electrical signals to light are optics. On 21 October 2026 NVIDIA announced capacity deals with six partners in four of these categories: substrate agreements with Ibiden, Samsung Electro-Mechanics and Unimicron that "will, in aggregate, drive a 2.5x increase in capacity over the next three years," of which the Ibiden deal had been signed earlier in the year; a packaging expansion at Amkor; a "$1.1 billion capacity reservation advance to KYEC" for new US testing plants; and a 15 times expansion of SPIL's optical engine capacity by mid 2027 (NVIDIA release, 21 October 2026). A capacity reservation advance is cash paid up front to fund a supplier's new line in exchange for a guaranteed share of what it makes. NVIDIA, which is paid at delivery by its customers, now pays its own suppliers years ahead.

NVIDIA

NVIDIA designs the chip, the rack, the network gear and much of the software. Its gross margin was 75.0 percent in the quarter ended 26 July 2026, and it has sat between 73 and 78 percent in 11 of the last 12 quarters; the exception was the quarter ended April 2025, when a $4.5 billion charge for H20 chips it could no longer sell to China pulled the margin to 60.5 percent (NVIDIA CFO commentary, Q2 FY2027). Data center revenue rose from $14.5 billion in the quarter ended October 2023 to $89.0 billion in the quarter ended July 2026, when it was 92.5 percent of the company (NVIDIA 10-Q, quarter ended 26 July 2026).

Behind that revenue sit promises to suppliers. As of 26 July 2026 NVIDIA's supply commitments were $279 billion, up from $119 billion a quarter earlier, "primarily memory and manufacturing facilities." By NVIDIA's fiscal years, $92 billion falls in the rest of fiscal 2027, $87 billion in fiscal 2028 and $88 billion in fiscal 2029, so about 96 percent falls due by late January 2029 (same 10-Q). The seed version of this report said those bills were NVIDIA's whether or not customers slowed their orders. The filing is more careful: "in certain instances, these agreements may be cancelable, rescheduled, or adjustable for our business needs prior to placing firm orders." No split is given, so a large but undisclosed share is fixed. The H20 episode is the precedent for what a demand shock does: a $4.5 billion charge, far below the commitments then outstanding, rather than the full face value. NVIDIA's inventory was $31.6 billion at July 2026, most of it raw materials and work in process, not finished boxes (same 10-Q).

The figure below shows the quarterly data center revenue against the supply commitments that stand behind it.

NVIDIA data center revenue per quarter and its promises to suppliers, $ billionsBars: data center revenue each quarter, Oct 2023 to Jul 2026. Line: supply and capacity commitments at quarter end (definition widened in mid 2025, so early and late points are not strictly comparable).NVIDIA data center revenue per quarter and its promises to suppliers, $ billionsBars: data center revenue each quarter, Oct 2023 to Jul 2026. Line: supply and capacity commitments atquarter end (definition widened in mid 2025, so early and late points are not strictly comparable).$0B$20B$40B$60B$80B$100B$0B$100B$200B$300BQ3FY24 (ended 2023-10-29): data center revenue $14.5B, GAAP gross margin 74%Q3FY24Q4FY24 (ended 2024-01-28): data center revenue $18.4B, GAAP gross margin 76%Q1FY25 (ended 2024-04-28): data center revenue $22.6B, GAAP gross margin 78.4%Q1FY25Q2FY25 (ended 2024-07-28): data center revenue $26.3B, GAAP gross margin 75.1%Q3FY25 (ended 2024-10-27): data center revenue $30.8B, GAAP gross margin 74.6%Q3FY25Q4FY25 (ended 2025-01-26): data center revenue $35.6B, GAAP gross margin 73%Q1FY26 (ended 2025-04-27): data center revenue $39.1B, GAAP gross margin 60.5%Q1FY26Q2FY26 (ended 2025-07-27): data center revenue $41.1B, GAAP gross margin 72.4%Q3FY26 (ended 2025-10-26): data center revenue $51.2B, GAAP gross margin 73.4%Q3FY26Q4FY26 (ended 2026-01-25): data center revenue $62.3B, GAAP gross margin 75%Q1FY27 (ended 2026-04-26): data center revenue $75.2B, GAAP gross margin 74.9%Q1FY27Q2FY27 (ended 2026-07-26): data center revenue $89.0B, GAAP gross margin 75%$279B$17BData center revenue, $B per quarter (left)Supply commitments at quarter end, $B (right)Sources: NVIDIA CFO commentary for each quarter (8-K exhibits); 10-Q for the quarter ended 26 Jul 2026, Note 10. Hover a bar.
Figure 3. NVIDIA's data center revenue each quarter from the quarter ended October 2023 to the quarter ended July 2026 (bars, left axis), and the supply and capacity commitments it had promised its suppliers at each quarter end (line, right axis). Revenue rose from $14.5 billion to $89.0 billion a quarter; commitments rose from $17 billion to $279 billion. Sources: NVIDIA CFO commentary exhibits and the 10-Q for the quarter ended 26 July 2026.
Table view: NVIDIA data center revenue and supply commitments by quarter
QuarterQuarter endData center revenue ($B)GAAP gross margin (%)Supply commitments ($B)
Q3FY242023-10-2914.57417.11
Q4FY242024-01-2818.47616.1
Q1FY252024-04-2822.678.418.8
Q2FY252024-07-2826.375.127.8
Q3FY252024-10-2730.874.628.9
Q4FY252025-01-2635.67330.8
Q1FY262025-04-2739.160.529.8
Q2FY262025-07-2741.172.445.8
Q3FY262025-10-2651.273.450.3
Q4FY262026-01-2562.37595.2
Q1FY272026-04-2675.274.9119
Q2FY272026-07-2689.075279

NVIDIA's rivals

AMD signed a "definitive agreement" with OpenAI in October 2025 for up to 6 gigawatts of AMD chips. The deal came with a warrant, the right to buy shares later at a set price, for up to 160 million AMD shares at one cent each, vesting in steps as chips are bought and as AMD's share price hits targets up to $600 (AMD 8-K, 6 October 2025). Meta signed the same shape in February 2026 (AMD 8-K, 24 February 2026), and as of 27 June 2026 "no warrant tranches had vested or become exercisable" (AMD 10-Q). Google's TPU is designed with Broadcom, whose AI chip revenue grew 221 percent year on year to $16.7 billion in its quarter ended August 2026 (Broadcom Q3 FY2026 release); Anthropic will "access through Broadcom approximately 3.5 gigawatts" of TPU capacity from 2027, with the filing adding that Anthropic's use "is dependent on Anthropic's continued commercial success" (Broadcom 8-K, 6 April 2026). Amazon's Trainium chip is the third rival: Anthropic can "secure up to 5 gigawatts" of it (Anthropic, 20 April 2026), and Amazon says OpenAI "has committed to consuming two gigawatts of Trainium capacity" from 2027 (Amazon).

Servers, racks and the pod

Somebody has to bolt the parts into a finished computer and a finished rack. Foxconn, Quanta and Wistron in Taiwan do most of it, and Dell, HPE and Supermicro sell finished servers under their own names. This is the low margin end of the chain. Foxconn's gross margin was 6.12 percent in the quarter ended June 2026, against NVIDIA's 75.0 percent in its overlapping quarter ended July 2026 (Foxconn release, 12 August 2026). Dell's was 20.9 percent, and its AI server backlog, meaning orders taken but not yet delivered, was a record $95 billion (Dell Q2 FY2027).

At GTC Berlin on 21 October 2026 NVIDIA showed a prefabricated design called DSX POD. Seventeen partners, including Dell, HPE, Lenovo, Schneider Electric, Vertiv and Foxconn, will build a Vera Rubin cluster inside containers, test it in the factory and ship it, cutting deployment "at a prepared site from six months to as little as 14 days," with deliveries "in early 2027" (NVIDIA release, 21 October 2026). The 14 days start only after the site is ready. The pod does not create a power hookup.

Export controls in one paragraph

The United States requires a license to ship NVIDIA's data center chips to China. In January 2026 the Commerce Department moved the H200 to case by case review. NVIDIA says its licensed H200 shipments were "less than 1% of Data Center revenue" in the quarter ended July 2026, that it took a $0.4 billion charge because China's government then restricted purchases, and that the chips pay "a 25% tariff upon importation" for inspection in the United States (NVIDIA 10-Q). A 2025 understanding under which US officials expected 15 percent or more of licensed China revenue was never written into a regulation (NVIDIA 10-K). Blackwell and Rubin remain unlicensed for China. So China is a small, licensed, tariffed channel for older chips and a closed door for the current ones, and the $4.5 billion H20 charge is the precedent for what a closed door costs.

Demand: who pays for the hours

Someone has to pay for the hours. A chip in a building earns nothing until a buyer pays for its time or for the answers it produces. This section asks who the buyers are, what they have signed, what the same gigawatt costs depending on who is asking, and what could make the buyers go away.

The buyers

Hyperscalers building for themselves. Capital expenditure, or capex, is money a company spends on long lived things such as buildings, servers and chips. It is paid now and counted as a cost slowly over the years the thing is used. A hyperscaler's capex is the clearest public number for how much it is building, and the 2026 guidance is the latest reading. Microsoft's finance chief put calendar 2026 at "approximately $175 billion" and said "roughly two thirds of our capex was for short-lived assets, primarily CPUs and GPUs" (Microsoft FY26 Q4 call). Alphabet guided to "$195‑205 billion" and said 60 percent of its infrastructure spending was servers and 40 percent data centers and networking (Alphabet Q2 2026 transcript). Amazon said "approximately $220 billion in cash CapEx in 2026," up from $200 billion because of "the higher cost of memory" (Amazon Q2 2026 call). Meta guided to $135 billion to $145 billion (Meta Q3 2026 release). Oracle's $90 billion to $95 billion for its fiscal 2027, with net cash capex of no more than $70 billion after customer prepayments, comes from call summaries; its release gives only the quarter's $28.5 billion (Oracle Q1 FY2027 release). Add them up: 175 + 195 + 220 + 135 + 70 = $795 billion at the low end, using Oracle's net cash figure, and 175 + 205 + 220 + 145 + 95 = $840 billion at the high end. The fiscal years and definitions differ (Oracle's figure is its fiscal year to May 2027, and Microsoft's includes finance leases), so treat that as an order of magnitude: five companies plan to spend about $800 billion in a year.

The figure below shows that spending by company from 2022 through the 2026 guidance.

Hyperscaler capital expenditure, 2022 to 2026 guidance, $ billionsCash spent on property and equipment by fiscal year from 10-K filings; the 2026 bar is each company's own guidance (midpoint of a range). Mixed fiscal years, so read as scale, not a sum.Hyperscaler capital expenditure, 2022 to 2026 guidance, $ billionsCash spent on property and equipment by fiscal year from 10-K filings; the 2026 bar is each company's ownguidance (midpoint of a range). Mixed fiscal years, so read as scale, not a sum.$0B$50B$100B$150B$200BMicrosoft 2022: $23.886BAlphabet 2022: $31.485BAmazon 2022: $63.645BMeta 2022: $31.186BOracle 2022: $4.511B2022Microsoft 2023: $28.107BAlphabet 2023: $32.251BAmazon 2023: $52.729BMeta 2023: $27.045BOracle 2023: $8.695B2023Microsoft 2024: $44.477BAlphabet 2024: $52.535BAmazon 2024: $82.999BMeta 2024: $37.256BOracle 2024: $6.866B2024Microsoft 2025: $64.551BAlphabet 2025: $91.447BAmazon 2025: $131.819BMeta 2025: $69.691BOracle 2025: $21.215B2025Microsoft 2026 (guidance): $175BAlphabet 2026 (guidance): $200BAmazon 2026 (guidance): $220BMeta 2026 (guidance): $140BOracle 2026 (guidance): $92.5B2026 guideMicrosoftAlphabetAmazonMetaOracleSources: SEC XBRL company facts (10-Ks); 2026 guidance from earnings calls and releases; Oracle FY2027 guidance via call summaries (secondary).
Figure 2. Capital expenditure by the five largest buyers, 2022 to 2025 actuals from filings and 2026 company guidance (lighter bars; midpoint where a range was given; Microsoft is calendar 2026 including finance leases, Oracle is fiscal 2027 to May 2027). Sources: SEC XBRL company facts; earnings calls and releases listed in the data file.
Table view: Capex by company and year ($B)
Company20222023202420252026
Microsoft23.88628.10744.47764.551175
Alphabet31.48532.25152.53591.447200
Amazon63.64552.72982.999131.819220
Meta31.18627.04537.25669.691140
Oracle4.5118.6956.86621.21592.5

They are building against signed promises from their own customers. Remaining performance obligations, or backlog, is revenue a company has signed contracts for but not yet earned. Microsoft's commercial backlog was $678 billion at June 2026, up 84 percent in a year (Microsoft FY26 Q4 release). Google Cloud's was $514 billion, with "just over 50%" expected to become revenue within 24 months (Alphabet transcript). Amazon Web Services' was $496 billion (Amazon call). Oracle's was $664 billion at 31 August 2026 (Oracle Q1 FY2027 release); the seed of this report had $455 billion, which was a year out of date. Oracle's filings do not name OpenAI.

Labs renting. A lab is a company whose main product is an AI model: OpenAI, Anthropic, Moonshot, and xAI, which is now part of SpaceX as SpaceX.AI. Labs mostly rent chips rather than own them. Anthropic's registration statement for a share sale, filed 26 October 2026, is the first lab filing with audited numbers. Revenue was $386 million in 2024, $4,585 million in 2025 and $11,555 million in the second quarter of 2026 alone (Anthropic S-1, accession 0001628280-26-067168). The same filing lists what Anthropic has promised to pay for compute: at least $44.9 billion to Microsoft between November 2026 and May 2033 "regardless of actual usage"; at least about $114.5 billion to Google and at least $110.0 billion to Amazon, each with a true up, meaning that if actual spend falls short Anthropic pays the difference; up to $120.5 billion to SpaceX.AI into 2029, which either party may cancel on 90 days' notice after initial periods ending in early 2027; up to about $44.6 billion to Nscale and about $41.3 billion to Lambda, "with fees accruing only as capacity is delivered to and accepted by us"; and about $161.2 billion of rent under five year equipment leases arranged through Broadcom. The filing also says: "In the past, we have significantly underestimated our compute requirements."

OpenAI is private and publishes no audited figures. Its reported revenue run rate, meaning a recent month's revenue multiplied by twelve, was "above $40 billion" in August 2026, "nearly $70 billion" in one report on 29 September and "about $50 billion" in others on 8 October (Yahoo Finance on the Axios report); the figures conflict. Its commitments are a mix of kinds. Microsoft's filing says OpenAI "contracted to purchase an incremental $250 billion of Azure services," a definitive agreement (Microsoft 10-Q, September 2025). The reported $300 billion Oracle deal is press reporting; Oracle's filings do not name the customer. Broadcom's 10 gigawatt deal was "a term sheet," which lists main terms but is not the final contract (Broadcom release). The NVIDIA deal, "at least 10 gigawatts" and "up to $100 billion," was a letter of intent, a statement that two parties plan to make a deal (NVIDIA release, 22 September 2025); Huang later said it was "never a commitment" (Fortune, 2 February 2026). A letter of intent, a term sheet and a definitive agreement are different things, and a headline will call all of them a deal.

Those two lists together show the part of the machine that does not yet run on its own. The industry's working story is a flywheel: release a model, earn token revenue, fund the next training run out of it. At current scale the loop does not close at any lab, and the Anthropic filing makes the gap measurable for the first time. Revenue grew about twelvefold in 2025, to $4.6 billion, and the single quarter ended June 2026 exceeded all of 2025; hold that quarter flat and the pace is about $46 billion a year. The compute promises listed above sum to roughly $640 billion on their maximum readings through 2033, and they differ in firmness: the Microsoft, Google and Amazon minimums are owed regardless of usage, the SpaceX.AI line is cancelable on 90 days' notice, the Nscale and Lambda fees accrue only as capacity arrives. Revenue can grow into that, and has been; it has not yet, and the instrument that bridges the gap is the document these numbers come from, a registration statement for a share sale. The next training run is funded by new capital, not by the last model's revenue, which is why a lab failing to refinance appears in section 11 as a break condition and not a footnote.

Enterprises and consumers. At the end of the chain are the people paying for tokens and subscriptions. Menlo Ventures estimates companies spent $37 billion on generative AI in 2025, up from $11.5 billion in 2024 (Menlo Ventures, 9 December 2025), and Google said its products process "over 3.2 quadrillion" tokens a month, up seven times in a year (Pichai, Google I/O, 19 May 2026).

Three prices for the same gigawatt

There are three prices for the same gigawatt, and they answer three different questions. A gigawatt year here means one gigawatt of data center power running for one year, and prices "per gigawatt" mean dollars a year for the computing that one gigawatt can run. One caution runs through all of them: a seller usually divides by the chip power it is contracted to supply, and a site's grid draw is 10 to 20 percent higher, so the same deal looks 10 to 20 percent cheaper per gigawatt of site power than per gigawatt of chip power. Goldman's notes are not public, so the basis of its figures is not known.

Short rent is what a buyer pays for hours it can stop buying soon, often within 90 days. It is high when live chips are scarce. CoreWeave's own investor presentation of 17 September 2026 gives the "recent pricing range for signed short-dated contracts (3-6 months) in Q3" as about $40 million per megawatt a year, "calculated as annualized revenue divided by power required to service clusters" (CoreWeave 8-K, 17 September 2026). $40 million per megawatt is $40 billion per gigawatt, on whatever power basis CoreWeave uses for "power required to service clusters." Goldman Sachs is reported, in a Yahoo Finance video segment, to put short term capacity at $40 billion to $50 billion a gigawatt (Yahoo Finance, 14 October 2026); the note itself is not public.

A multi year contract is what a buyer pays when it locks in years of supply. The customer accepts a lower price in exchange for a locked supply. The seller accepts a lower price in exchange for a locked bill. The same video says longer leases "sign around 20 billion per gigawatt"; that line is not explicitly tied to Goldman in the transcript, and the seed's "$20 billion to $30 billion" range was not found anywhere. Real contracts sit at or below that. IREN's five year deal with Microsoft is about $9.7 billion for about 200 megawatts of chip power, as reported (Cape Fear Advisors on IREN's filing, 25 October 2026). That is $9.7 billion ÷ 5 years = $1.94 billion a year; ÷ 0.2 gigawatts = about $9.7 billion per gigawatt year. It is the only public multi year price this report could find, and it is half the reported $20 billion level. A five year promise from the best credit in the market pays about a quarter of the short rent.

The owner's hurdle is what a site must earn each year for its owner to get a target return on what it cost to build. It is a minimum, not a market price. Goldman Sachs, per two secondary writeups of a note dated 25 September 2026, assumes a 15 percent return on "an average upfront capex cost of approximately $42 billion per GW" and gets "roughly $11.6 billion in annual revenue per gigawatt" (BigGo Finance; Crypto Briefing). Check the arithmetic: 15 percent of $42 billion is $6.3 billion, so the $11.6 billion must also cover depreciation of the chips and the site's operating cost; that is an inference, since the note is not public.

Huang at GTC Berlin on 21 October 2026 said "a one gigawatt AI factory costs about $50 billion" and "it's $40 billion per year of revenue generation that comes out of that infrastructure" (keynote transcript). That is a revenue figure, and it matches the short rent headline, not the owner's return; it is also a different claim from NVIDIA's own $40 billion of sales per gigawatt. Builders do not approve projects on the short rent price. Short rent is high because power and live chips are scarce. It is not a promise that the next gigawatt will clear at the same price.

The figure below puts the prices side by side: NVIDIA's sales into a gigawatt, the three rents, and the build cost.

One gigawatt, many prices: what the same gigawatt costs or earns, $ billionsEach bar is a different question about the same gigawatt: what the chips cost, what the whole site costs, what a renter pays per year, what the owner needs per year, what the landlord and the utility get.One gigawatt, many prices: what the same gigawatt costs or earns, $ billionsEach bar is a different question about the same gigawatt: what the chips cost, what the whole site costs,what a renter pays per year, what the owner needs per year, what the landlord and the utility get.$0B$10B$20B$30B$40B$50B$60BShort rent, 3 to 6 month deals (CoreWeave ~$40M/MW-yr; SpaceX to Google ~$50 to 60B derived). CoreWeave 8-K 17 Sep 2026; SpaceX FWP 5 Jun 2026, derivedShort rent, 3 to 6 month deals (CoreWeave ~$40M/MW-yr; SpaceX to Google ~$50 to 60B derived)Build cost, one gigawatt with chips (Bloomberg ~$30B; Epoch $37.9B; Goldman ~$42B; Huang $50B). Bloomberg/Cushman (secondary); Epoch AI; Goldman via BigGo (secondary); Huang GTC BerlinBuild cost, one gigawatt with chips (Bloomberg ~$30B; Epoch $37.9B; Goldman ~$42B; Huang $50B)NVIDIA content per gigawatt (Grace Blackwell $25B; Vera Rubin $40B). NVIDIA Q2 FY2027 call, 26 Aug 2026NVIDIA content per gigawatt (Grace Blackwell $25B; Vera Rubin $40B)Multi year contract (Goldman "around 20 billion" per year; IREN to Microsoft ~$9.7B). Yahoo Finance video on Goldman note (secondary); IREN 8-K via reports, derivedMulti year contract (Goldman "around 20 billion" per year; IREN to Microsoft ~$9.7B)Owner's hurdle: revenue a site needs per year (Goldman ~$11.6B at 15% on $42B). Goldman via BigGo and Crypto Briefing, 25 Sep 2026 (secondary)Owner's hurdle: revenue a site needs per year (Goldman ~$11.6B at 15% on $42B)Shell rent per year (triple net $100 to $150/kW/month = $1.2 to $1.8B; CBRE reading ~$2.0B). CREFC E-Primer 2026; datacenterscouts reading of CBRE H1 2026Shell rent per year (triple net $100 to $150/kW/month = $1.2 to $1.8B; CBRE reading ~$2.0B)Electricity per year (Texas $593M; Virginia $882M at 2026 industrial rates). EIA Electric Power Monthly, Jan to Aug 2026; arithmeticElectricity per year (Texas $593M; Virginia $882M at 2026 industrial rates)Sources: CoreWeave 8-K; SpaceX FWP; NVIDIA call; Epoch AI; Goldman (secondary); CREFC; EIA. Rent, hurdle, shell, power are per year.
Figure 4. The same gigawatt carries many prices. A short rental earns about $40 to $60 billion a year while chips are scarce; a multi year contract about $10 to $20 billion a year; the owner needs about $11.6 billion a year to earn a 15 percent return on a $42 billion build; the landlord's shell earns $1 to $2 billion a year; the electricity costs $0.6 to $0.9 billion a year. NVIDIA's own content is $25 to $40 billion of a $30 to $50 billion build. Sources as listed; Goldman figures are from secondary writeups of its notes.
Table view: Prices and costs per gigawatt
ItemLow ($B)High ($B)Source
Short rent, 3 to 6 month deals (CoreWeave ~$40M/MW-yr; SpaceX to Google ~$50 to 60B derived)4060CoreWeave 8-K 17 Sep 2026; SpaceX FWP 5 Jun 2026, derived
Build cost, one gigawatt with chips (Bloomberg ~$30B; Epoch $37.9B; Goldman ~$42B; Huang $50B)3050Bloomberg/Cushman (secondary); Epoch AI; Goldman via BigGo (secondary); Huang GTC Berlin
NVIDIA content per gigawatt (Grace Blackwell $25B; Vera Rubin $40B)2540NVIDIA Q2 FY2027 call, 26 Aug 2026
Multi year contract (Goldman "around 20 billion" per year; IREN to Microsoft ~$9.7B)9.720Yahoo Finance video on Goldman note (secondary); IREN 8-K via reports, derived
Owner's hurdle: revenue a site needs per year (Goldman ~$11.6B at 15% on $42B)11.611.6Goldman via BigGo and Crypto Briefing, 25 Sep 2026 (secondary)
Shell rent per year (triple net $100 to $150/kW/month = $1.2 to $1.8B; CBRE reading ~$2.0B)1.22.0CREFC E-Primer 2026; datacenterscouts reading of CBRE H1 2026
Electricity per year (Texas $593M; Virginia $882M at 2026 industrial rates)0.590.88EIA Electric Power Monthly, Jan to Aug 2026; arithmetic

The SpaceX and Google deal, step by step

One contract shows how a headline, a rent and a commitment differ. On 5 June 2026 SpaceX filed this text: "we entered into a Cloud Service Agreement with Google LLC with respect to access to compute capacity. The compute capacity provided includes approximately 110,000 NVIDIA GPUs, CPUs, memory, and other related components. Pursuant to the agreement, the customer has agreed to pay us $920 million per month from October 2026 through June 2029, with capacity ramping up through September at a reduced fee. ... After December 31, 2026, the agreement may be terminated by either party upon 90 days' notice." (SpaceX free writing prospectus, 5 June 2026). It was filed as a free writing prospectus, a document a company selling shares files to tell investors something material, not as an 8-K.

The price per chip hour. A month has 8,760 ÷ 12 = 730 hours. Google buys 110,000 × 730 = 80,300,000 GPU hours a month. $920,000,000 ÷ 80,300,000 = $11.46 per GPU per hour. That price includes the CPUs, memory, networking, building and power, not the chip alone. For comparison, CoreWeave's public walk in price for a GB200 was $10.50 per GPU per hour on 27 October 2026 (CoreWeave pricing). Google is paying at or above the walk in price.

The price per gigawatt. $920 million × 12 = $11.04 billion a year. The filing does not say which chip Google gets, but SpaceX's prospectus says its first cluster of about 110,000 GB200 chips drew about 210 megawatts and a later 110,000 GB300 cluster drew 220 megawatts, counting chip power only. $11.04 billion ÷ 0.21 gigawatts = about $52.6 billion per gigawatt year; ÷ 0.22 = about $50.2 billion. Using this report's own rack figure instead, 110,000 GPUs ÷ 72 per rack × 120 kilowatts = about 183 megawatts, and $11.04 billion ÷ 0.183 = about $60 billion. So the Google deal sits at about $50 billion to $60 billion per gigawatt year of chip power depending on the chip, which the filing does not identify, and lower per gigawatt of whole site power, since cooling is excluded. Either way it is at or above the top of the short rent range.

The commitment. The full term, October 2026 through June 2029, is 33 monthly payments if both end months count, and 33 × $920 million = $30.36 billion, which is where the "$30 billion" headlines came from. But the earliest exit is notice given just after 31 December 2026, ending about 1 April 2027. The locked months are October through March, six of them: 6 × $920 million = $5.52 billion. The firm commitment is about 18 percent of the headline. At the Goldman conference SpaceX's finance chief described the newer deals the same way, "in essence, 90-day with a 90-day out, so roughly six-month commits," and announced one at "about $1.11 billion a month" (transcript). That deal annualizes to $1.11 billion × 12 = $13.32 billion, and its locked part is six months of fees, $1.11 billion × 6 = $6.66 billion.

Contract types, with the filings

A take or pay contract says the customer pays for reserved capacity whether or not it uses it. CoreWeave's quarterly report defines its committed contracts that way, "requiring payment regardless of the level of utilization," and says they were 98 percent of its revenue in the second quarter of 2026 (CoreWeave 10-Q, quarter ended 30 June 2026). Even here there is a condition: Meta's order with CoreWeave pays "subject to ... satisfaction of delivery and availability of service requirements" (CoreWeave 8-K, 30 September 2025), so the bill is firm if CoreWeave delivers working capacity and not otherwise. A true up contract sets a minimum spend and makes the buyer pay any shortfall when the contract says it is due. A 90 day contract is the other kind. The customer holds the demand risk for the life of a take or pay contract. The seller holds it under a 90 day deal.

How long a chip lives on the books

Depreciation is the accounting charge that spreads the cost of a machine over the years it is expected to be useful. If a $30,000 chip is written off over six years, the yearly charge is $5,000. Over three years it is $10,000. A longer useful life makes reported profit higher today and changes nothing about the cash already spent.

The owners have lengthened their lives. Microsoft and Alphabet moved from three to four years to as long as six; Amazon moved to five to six, then cut a subset back to five in 2025 citing the faster pace of AI technology; Meta moved to 5.5 years, which cut its 2025 depreciation by about $2.9 billion; Oracle and CoreWeave use six; Nebius uses four (from the companies' annual reports, linked here through secondary summaries: Accounting Today; The Stack; Wccftech; StreetInsider). Michael Burry's claim, quoted by CNBC, is that the understatement across hyperscalers for 2026 to 2028 is about $176 billion (CNBC, 11 November 2025). Jim Chanos put it plainly: "If the chips last for three years, you have to depreciate a third of what you spend" (Yahoo Finance).

NVIDIA's written position, in a November 2025 memo to analysts reported by CNBC, is that customers depreciate over four to six years and that A100 chips from 2020 still run at high utilization (CNBC, 25 November 2025). The seed of this report said Huang tells lenders the life is seven or eight years; that is a reporter's paraphrase of an interview in which his verbatim words were about residual value being "really, really high" (Yahoo Finance, 24 October 2026). Only one lender's written assumption was found: CoreWeave's August 2026 credit agreement values the servers on a straight line over "a useful life of six (6) years" (CoreWeave DDTL 5.5 credit agreement), and the loans themselves run about five years.

The useful life under debate is not a property of the silicon; it is set by NVIDIA's release rhythm. Rack generations now arrive about a year apart, GB200 and then Vera Rubin, the 2026 generation, and each arrival resets what a year-old machine can earn against the newest one. A seller that is paid at delivery, whose customers write the same machine off over five or six years, and that ships a better machine every year, is in effect writing the depreciation schedule of its own customers' collateral. The repricing has not bitten: H100 rents rose about 44 percent from December 2025 to October 2026 (section 8) and NVIDIA says its 2020 chips still run busy, because demand has outgrown supply. That is the condition doing the work. In the first year supply catches demand, the annual cadence stops being harmless and becomes the thing that reprices every loan in section 6.

What can shrink demand

Two different shocks hit two different lines, and a third removes the buyer from the outside.

A model good enough to live on a phone removes a class of jobs from the data center. Alibaba's Qwen 3.5 small models, released in early March 2026, were built for this; the 4 billion parameter version runs offline on an iPhone with 8 gigabytes of memory (Qwen3.5-4B model card) at a measured 15 to 18 tokens a second (Loci measurements); the seed's 20 to 30 was unsourced, and Loci is a company I have reviewed as a deal. Apple's Foundation Models of 8 June 2026 include an on device 3 billion parameter model and a 20 billion parameter model that turns on 1 to 4 billion per token, and apps can call them directly (Apple, 8 June 2026). The seed said what had not happened was Apple making such a model the default for ordinary chat, mail and search. Since 14 September 2026, Siri AI is Apple's default assistant, in beta, and it runs "on device and on servers using Private Cloud Compute" (Apple newsroom, 14 September 2026), with the hardest work running on NVIDIA GPUs in Google Cloud (Apple research post above). So Apple's default moved work into Apple's and Google's data centers rather than off them. The phone takes the easy jobs. Harder work stays in the building.

A cheaper frontier model cuts the price and still needs a factory. Moonshot's Kimi K3.1 Pro, released 23 October 2026, keeps the K3 base of 2.8 trillion parameters with about 104 billion active per token; Moonshot itself calls it "3T-class" (Moonshot blog; DataCamp). On the Artificial Analysis Intelligence Index it scored 55, fourth place: behind Claude Opus 5.5 at 58 at its highest setting, and behind Claude Sonnet 5.5 and Meta's Muse Wonder Full at 56; tied with or ahead of GPT-6 Astra, Claude Fable 5.1 and Gemini 4 Argon at 53 (Artificial Analysis leaderboard). Its cost per test task was $2.11, against $3.26 for GPT-6 Astra, $5.98 for Opus 5.5 and $7.63 for Fable 5.1 at their highest settings; Opus 5.5 at its "high" setting scores 54 for $1.82, cheaper than Kimi. Moonshot said the weights would be public by 4 November 2026, and as of 27 October they were not. The precedent for what an open model does to the chain is DeepSeek: on 27 January 2025 NVIDIA fell about 17 percent, about $589 billion of market value, per press reports (Motley Fool).

Those tokens are still produced on a cluster. The open model moves the margin from the closed lab's price list toward whoever owns power and chips. The building can stay busy while the rent per gigawatt falls from the scarcity price toward the revenue a builder needs, about $12 billion a year. Nothing stops rent from falling through that level; that is the case in which the builder misses its target.

A recession or a pause in corporate spending does the same job from the other side. It removes the buyer before the model does. MIT's NANDA study of 2025 found that despite $30 billion to $40 billion of enterprise investment in generative AI, "95% of organizations are getting zero return" (MIT NANDA, State of AI in Business 2025); it counted pilots with no measured profit and loss effect in a short window, from about 300 initiatives and 153 survey responses, and it is one contested survey, not proof that the spending earns nothing. Ramp, a company that issues corporate cards and publishes what its business customers spend, shows the two lines in its own index: the blended price its customers paid OpenAI and Anthropic per million tokens fell from $0.86 to $0.64, a 25 percent drop, between the week ending 13 September and the week ending 11 October 2026, while total token spending rose 23 percent over the same month and the share of businesses paying for AI reached 55.9 percent in September (Ramp AI Index). No evidence of an actual 2026 cut in enterprise AI spending was found for this report. Anthropic's own filing says: "We expect our revenue growth rate to decline over time, and it may decline significantly" (Anthropic S-1). Price per token for a fixed skill falls roughly ten times a year or faster while Google's monthly token count rose about seven times in a year; spending can rise, flatten or fall depending on which moves faster, and in Ramp's latest month volume won.

Financing: how the money shows up

A lender hands over cash for one of two reasons. A named customer has already promised to pay. Or the lender can take the equipment and sell it if the borrower does not pay. Future demand that nobody has signed for supports equity only.

The words

Equity is money put in by an owner in exchange for a share of whatever is left after everyone else is paid. The owner can lose all of it and has no date by which it must be repaid. Debt is money borrowed with a promise to pay it back on set dates with interest; if the borrower misses a payment, the lender can take the things pledged to it. Those pledged things are collateral. A guarantee is a promise by a third party to pay if the borrower does not.

SOFR, the Secured Overnight Financing Rate, is the rate at which banks and funds lend each other cash overnight against Treasury bonds, published every business day by the New York Fed. It was 3.93 percent on 26 October 2026 (New York Fed). Most big floating rate loans are priced as SOFR plus a fixed extra amount, called the spread, which pays the lender for the risk that this borrower fails. A basis point is one hundredth of one percent, so 100 basis points is 1 percent. At SOFR plus 2.25 percent a loan costs 3.93 + 2.25 = 6.18 percent today, or $61.8 million a year per $1 billion borrowed. At SOFR plus 5.50 percent it costs 9.43 percent, or $94.3 million. The 325 basis point gap is $32.5 million a year per $1 billion.

A delayed draw term loan is a loan where the lender promises a maximum up front but the borrower takes the cash in pieces, as each batch of chips is delivered. CoreWeave's March 2026 loan promised $8.5 billion, but only $2.837 billion was drawn at 30 June 2026 (CoreWeave 10-Q). A finance lease is a lease that is in substance a purchase on credit, for example because it covers most of the asset's useful life; the lessee shows the asset and a debt on its own books. A special purpose vehicle is a company created for one job, such as owning one set of servers and one customer contract, so that lenders to it are paid only from that job and the parent's other creditors cannot reach those assets. A debt is off balance sheet when a company is economically tied to it but it does not appear as the company's own debt, usually because it sits in a vehicle the company does not control.

A credit rating is a letter grade from an agency such as Moody's, S&P, Fitch or DBRS on how likely a borrower or a loan is to pay. On Moody's scale, A means low credit risk, Baa is the lowest investment grade tier, and Ba means speculative; the digits 1, 2, 3 mark the top, middle and bottom of each tier, and everything below Baa3 is called high yield, or junk. The debt service coverage ratio is the cash a project earns after operating costs divided by the interest and principal due in the same period; 1.15x means $115 of cash for every $100 owed. The advance rate is the loan as a share of what the collateral cost; at 90 percent, $1 billion of servers supports a $900 million loan and the owner puts up the other $100 million as equity. A cash trap means the customer pays into a bank account the lender controls and anything left after the lender is paid stays there rather than going to the owner if something goes wrong.

What the interest rate is actually pricing

The chip can be identical and the spread the lender charges can still more than double, taking the all in rate up by half. The rate follows the signature. CoreWeave's three loans of 2026, all from its filings, show it.

DDTL 4.0, March 2026. $8.5 billion. The borrower is CoreWeave Compute Acquisition Co. VIII, a subsidiary that owns the chips and the customer contract. The floating piece is SOFR plus 2.25 percent; the fixed piece is "approximately 5.9%." Moody's rated it A3 and DBRS A (low), "the first investment-grade rated financing secured by HPC infrastructure and an associated customer contract." The parent is liable only for "specified 'bad acts'" such as fraud or voluntary bankruptcy (CoreWeave 8-K and release, 31 March 2026). The filing redacts the customer; DBRS names Meta and calls the contract take or pay (DBRS). The credit agreement caps each draw at 90 percent of the cost of the servers, requires coverage of at least 1.15x, requires the borrower to send "the serial numbers with respect to the applicable racks of the GPU Servers" within 60 days of each draw, routes the customer's cash through a nine step waterfall with a cash trap account, and starts principal repayments early if a data center site is late (credit agreement).

DDTL 5.0, May 2026. $3.1 billion at SOFR plus 4.50 percent, for "two large, non-investment grade customers." Moody's Ba2, Fitch BB+. The parent guarantees it in full. Coverage must be at least 1.35x and the advance cap is 71.42 percent (CoreWeave 8-K, 15 May 2026; release; credit agreement).

DDTL 5.5, August 2026. $2.6 billion at SOFR plus 5.50 percent. Ba2 and BB+, parent guaranteed, 1.35x, advance cap 70 percent. The release states the difference plainly: the facility "carries an approximate five-year maturity while its underlying customer contracts average approximately three years in length," with lenders "signalling a willingness to underwrite renewal risk." The release does not name the customers; it calls them "a diverse group of leading AI, financial services, and technology customers" and does not call them weaker. The credit agreement values the servers on a six year straight line and traps cash if projected contract value falls below 2.40 times the loans (CoreWeave 8-K, 10 August 2026; release; credit agreement).

The seed of this report said the chips did not change and the promise did. That is right but incomplete. When the promise is weaker or shorter, the lender charges more, lends less against the same chips (90 percent of cost falling to 70), demands more cushion (1.15x rising to 1.35x), and insists on the parent's full guarantee instead of a bad acts carve out. The signature changes the price, the size and the cushion all at once. The older loans show where this started: CoreWeave's first loan, from 2023, ran at an average of 14.11 percent in 2024, with spreads in its 2024 loan set by the customer's rating, 6.00 to 6.50 percent for investment grade contracts and 13.00 percent for others (CoreWeave S-1, March 2025).

The figure below lays out that ladder: spread, advance rate and cushion by customer credit.

The signature sets the rate: CoreWeave's loans by what the customer promisedBars: all in floating rate today (SOFR 3.93% on 26 Oct 2026 plus the loan's spread). Labels: share of chip cost the lender will fund, and the cash cushion required. Same borrower, same kind of chips.The signature sets the rate: CoreWeave's loans by what the customer promisedBars: all in floating rate today (SOFR 3.93% on 26 Oct 2026 plus the loan's spread). Labels: share of chipcost the lender will fund, and the cash cushion required. Same borrower, same kind of chips.0%3%6%9%12%15%SOFR 3.93%DDTL 4.0, Mar 2026: SOFR 3.93%DDTL 4.0, Mar 2026: SOFR + 2.25% = 6.18% today. Customer: Meta take or pay (per DBRS). Advance rate: 90% of chip cost. Coverage: 1.15x. Rating: A3 / A (low). Parent liable: bad acts only.DDTL 4.0, Mar 2026. Behind it: Meta take or pay (per DBRS). Rating: A3 / A (low). Parent: bad acts only.SOFR + 2.25 = 6.18%; lends 90% of cost, 1.15x coverDDTL 3.0, Jul 2025: SOFR 3.93%DDTL 3.0, Jul 2025: SOFR + 4.00% = 7.93% today. Customer: OpenAI contract. Advance rate: . Coverage: n/a. Rating: no rating. Parent liable: full guarantee.DDTL 3.0, Jul 2025. Behind it: OpenAI contract. Rating: no rating. Parent: full guarantee.SOFR + 4.00 = 7.93%DDTL 5.0, May 2026: SOFR 3.93%DDTL 5.0, May 2026: SOFR + 4.50% = 8.43% today. Customer: two non investment grade customers. Advance rate: 71.42% of chip cost. Coverage: 1.35x. Rating: Ba2 / BB+. Parent liable: full guarantee.DDTL 5.0, May 2026. Behind it: two non investment grade customers. Rating: Ba2 / BB+. Parent: full guarantee.SOFR + 4.50 = 8.43%; lends 71.42% of cost, 1.35x coverDDTL 5.5, Aug 2026: SOFR 3.93%DDTL 5.5, Aug 2026: SOFR + 5.50% = 9.43% today. Customer: mixed; 3 yr contracts vs 5 yr loan. Advance rate: 70% of chip cost. Coverage: 1.35x. Rating: Ba2 / BB+. Parent liable: full guarantee.DDTL 5.5, Aug 2026. Behind it: mixed; 3 yr contracts vs 5 yr loan. Rating: Ba2 / BB+. Parent: full guarantee.SOFR + 5.50 = 9.43%; lends 70% of cost, 1.35x coverDDTL 2.0, May 2024: SOFR 3.93%DDTL 2.0, May 2024: SOFR + 6.00% = 9.93% today. Customer: priced by customer rating. Advance rate: . Coverage: n/a. Rating: no rating. Parent liable: full guarantee.DDTL 2.0, May 2024. Behind it: priced by customer rating. Rating: no rating. Parent: full guarantee.SOFR + 6.00 = 9.93%DDTL 1.0, Jul 2023: SOFR 3.93%DDTL 1.0, Jul 2023: SOFR + 9.62% = 13.55% today. Customer: early contracts. Advance rate: . Coverage: n/a. Rating: no rating. Parent liable: full guarantee.DDTL 1.0, Jul 2023. Behind it: early contracts. Rating: no rating. Parent: full guarantee.SOFR + 9.62 = 13.55%Sources: CoreWeave 8-Ks, credit agreements, 2025 S-1, Q2 2026 10-Q; DBRS 3 Apr 2026; New York Fed SOFR.
Figure 5. CoreWeave's loans ranked by what the customer behind each one promised. The loan backed by Meta's take or pay contract costs SOFR plus 2.25 percent, is rated A3, funds 90 percent of chip cost and needs 1.15 times coverage; the loans behind weaker or shorter contracts cost SOFR plus 4.50 to 5.50 percent, fund 70 to 71 percent of cost, need 1.35 times coverage and carry a full parent guarantee. Earlier loans ran SOFR plus 6.00 to 9.62 percent. Sources: CoreWeave filings; DBRS; New York Fed.
Table view: CoreWeave loan ladder
LoanCustomer behind itSpread over SOFRAll in todayAdvance rateCoverageRatingParent liable
DDTL 4.0, Mar 2026Meta take or pay (per DBRS)2.25%6.18%90%1.15xA3 / A (low)bad acts only
DDTL 3.0, Jul 2025OpenAI contract4.00%7.93%n/ano ratingfull guarantee
DDTL 5.0, May 2026two non investment grade customers4.50%8.43%71.42%1.35xBa2 / BB+full guarantee
DDTL 5.5, Aug 2026mixed; 3 yr contracts vs 5 yr loan5.50%9.43%70%1.35xBa2 / BB+full guarantee
DDTL 2.0, May 2024priced by customer rating6.00%9.93%n/ano ratingfull guarantee
DDTL 1.0, Jul 2023early contracts9.62%13.55%n/ano ratingfull guarantee

CoreWeave owed $35.551 billion of principal at 30 June 2026 and paid $640 million of net interest in that quarter on $2,575 million of revenue, so about a quarter of its revenue went to interest (10-Q). Its backlog was $103.7 billion. A credit default swap is insurance against a company defaulting, priced in basis points a year of the amount insured; press reports put CoreWeave's five year swap above 1,000 basis points in mid October 2026, meaning more than $1 million a year to insure $10 million of its debt (letsdatascience summary of Bloomberg and Reuters data; secondary only).

The same pattern repeats elsewhere. IREN financed its Microsoft contract at one month SOFR plus 2.25 percent, and two months later borrowed about $2.4 billion from Blue Owl and PIMCO for other customers "at a per annum rate equal to 9.0%" with a full parent guarantee (IREN 10-K, fiscal 2026). Lambda borrowed $1.008 billion at 6.78 percent fixed, rated Baa1, against "two investment-grade offtakers" (Lambda, 1 October 2026).

A loan drawn against a live contract keeps getting paid if the customer honors the signature. A loan drawn against a building that is not finished has a hole in the middle: interest runs, and the customer's bill may not have started. That is why CoreWeave's Meta loan can start principal payments early if the site is late.

One reading of this ladder is wrong and worth naming. The grades look like a spread of different risks: an A3 loan here, a Ba2 there, a book an investor might call diversified. But a rating here measures distance from a cash flow, and the cash flow is largely the same one. Strip the intermediation and most signatures in this section trace to a short list of payers: the labs' future model revenue, and the other income of the five or six companies that guarantee, prepay or take-or-pay on the labs' behalf, with NVIDIA's purchase promises and guarantees stitched across both. A lender holding the Meta-backed loan, the three-year-contract loan and a Lambda bond holds three seniorities of one bet, that model revenue grows into the commitments of section 5. If it does, every tranche pays. In the state of the world where it does not, the grades converge, and that is the state the spread was supposed to be pricing. These loans do not move with the stock index day to day, but as "What financing cannot do" notes below, the index is full of the same AI bet; low measured correlation in calm months is not low correlation in the month that matters.

Four ways the money shows up

The giant borrows as itself. Alphabet, Amazon, Meta and Oracle issue ordinary company bonds. The bondholder is lending to a company with ads, cloud, retail and software behind it, not to one cluster. From the pricing term sheets on EDGAR, the four sold about $237 billion of dollar bonds in ten offerings between September 2025 and August 2026, plus euro, sterling and other currency pieces; that total is my sum of the term sheet amounts (term sheets filed as free writing prospectuses; Meta's filings list, Alphabet's, Amazon's, Oracle's). Coupons on the 30 to 40 year pieces rose from about 5.5 to 5.75 percent in late 2025 to 6.2 to 6.5 percent by mid 2026, while the 30 year Treasury yield was 5.31 percent on 26 October 2026 (US Treasury daily yield curve). No registered bond offering by Microsoft was found on EDGAR for 2025 or 2026; the seed's list of four borrowers was wrong on that name. The giants also sold shares in 2026: Alphabet raised $84.75 billion of stock and mandatory convertible preferred, including $10 billion from Berkshire Hathaway, and Meta announced about $37.5 billion of common stock and preferred on 26 October 2026 (same EDGAR term sheets). Inside each company, the test for a site is whether it earns the owner's hurdle of about $12 billion a year per gigawatt.

Not all of a giant's commitments show as its debt. Meta holds a 20 percent interest in two ventures that are building campuses in Louisiana, for about $27 billion, and Texas, for about $14 billion, and leases the buildings back under leases with "an initial four-year term and renewal options that provide for a total lease period of up to 20 years." Because Meta does not control the ventures, it does not consolidate them. It has given residual value guarantees, promises to cover any shortfall between the buildings' value and a threshold if it walks away, of up to $41.493 billion, and its total maximum exposure to the ventures is $68.404 billion, against its own long term debt of $80.922 billion (Meta 10-Q, quarter ended 30 September 2026). Moody's estimated $662 billion of data center lease obligations signed but not yet started at the end of 2025 across Amazon, Meta, Alphabet, Microsoft and Oracle, equal to 113 percent of their adjusted debt, as reported by Fortune (Fortune via Yahoo, 25 February 2026). Oracle's credit default swap went from about 40 basis points in September 2025 to a record 288 on 15 October 2026, per press (Yahoo Finance).

The lab signs, and the landlord borrows. OpenAI and Anthropic do not have the credit of Microsoft. They get chips by promising to pay a landlord, or by renting from someone who already has them. The landlord's lender treats the lab's signature as the collateral and the chips as the backup. Anthropic's own filing shows the mechanism from the lab's side: Nscale "is required to use best efforts to obtain qualifying financing for the NVIDIA GPUs and data center infrastructure within a specified period," and the Lambda deal may be ended "if Lambda does not timely secure the facility lease" (Anthropic S-1). Nscale's own filing shows the resulting loan: $1.2 billion for a North Carolina site at three month SOFR plus 2.375 percent (Nscale S-1, 18 September 2026). If the contract is shorter than the loan, someone has to sign again at the end or the lender has a hole. That is DDTL 5.5: a five year loan against contracts averaging three.

A variant puts a giant behind a tenant it does not own. Google is not the tenant at TeraWulf's or Cipher's sites; Fluidstack is. Google "will backstop" Fluidstack's lease obligations up to a cap, $3.2 billion at TeraWulf and $1.73 billion at Cipher, and is paid in warrants on the landlords' shares (TeraWulf 8-K, 14 August 2025; Cipher, November 2025). TeraWulf's subsidiary then sold $3.2 billion of 7.750 percent notes against that lease (TeraWulf, 16 October 2025). The landlord borrows as if Google had signed.

The owner with other income holds the long bill and rents short. On 24 October 2026 SpaceX "entered into a binding commitment letter to enter into a master finance lease with an entity managed by Apollo Global Management," under which the lessor buys GPU pods and leases them to SpaceX. Each batch has "a term of approximately five to five and one-quarter years from the applicable commencement date." Rent is paid quarterly in advance and equals "one-twentieth of the financed cost of the applicable tranche" plus interest at a fixed rate not yet set. Total principal is "approximately $40 billion," closing is expected before year end, and the schedules "are expected to commence during the first half of 2027 upon delivery of the GPUs" (SpaceX 8-K, 26 October 2026). One twentieth per quarter means the whole cost is repaid over 20 quarters, five years: on $40 billion that is $2 billion a quarter, $8 billion a year, plus interest. Apollo's release names Goldman Sachs as sole structuring agent and funds managed by BlackRock, Goldman Sachs Asset Management and KKR as anchors, and says the chips include Vera Rubin (Apollo, 26 October 2026).

SpaceX already carried $38.989 billion of debt and finance leases at 30 September 2026, including $12.897 billion of chip leases with Valor Equity Partners booked as debt, so the Apollo lease roughly doubles its debt once drawn (SpaceX 10-Q, quarter ended 30 September 2026). It can sign this because lenders trust Starlink and the launch business. It then rents the hours out on contracts "typically three years and terminable by either party upon 90 days' notice" (same 10-Q). The customer is in for a quarter. Apollo is in for five years. On 25 October 2026 Elon Musk wrote on X, replying to Chamath Palihapitiya: "As of the past few weeks, debt markets have almost entirely shut off access to money for any company that doesn't have substantial revenue independent of AI data centers. SpaceX closed $40B of debt for GPUs, but we're investment grade and have Starlink & launch revenue. That means the 200+ neoclouds are going to see guppy-level death and consolidation. Some will make it through, but not many." (Musk on X, 25 October 2026). A neocloud is a company whose whole business is renting out AI chips, such as CoreWeave, Nebius, Lambda, IREN, Crusoe or Nscale. He wrote "closed"; the filing says a commitment expected to close by year end.

NVIDIA helps the customer borrow, so NVIDIA can ship. This is the circular piece. The chip seller stands behind the buyer's rent, or agrees to buy hours the buyer cannot sell. As of the quarterly report for 26 July 2026 and the August guarantees disclosed with it (NVIDIA 10-Q; NVIDIA 8-K, 17 August 2026):

A separate plan announced on 10 August 2026 with Apollo, BlackRock, Blackstone, Brookfield, Goldman Sachs and KKR aims to "mobilize more than $500 billion of third-party capital over time." Those were memorandums of understanding, and the 10-Q says they "may not lead to definitive agreements" (NVIDIA release, 10 August 2026). No definitive agreement was found as of 27 October 2026. Read them as a wish until they are contracts.

Two more lines from the filings show the posture shifting inside one year. The 10-K filed in February 2026 said "We have not entered into any financing arrangements" (NVIDIA 10-K). Six months later the 10-Q, while keeping the standard term of payment shortly after delivery, says that for investment grade customers with large data center builds NVIDIA has given payment terms "ranging from 90 days up to one year," and one direct customer was 16 percent of NVIDIA's revenue in the quarter (NVIDIA 10-Q).

The seed cited a CNBC summary of the filing to the effect that NVIDIA pays only if a project party defaults or if live hours go unsold. That article was not found, but the filing text supports the sense of it: the guarantees trigger on default, and the cloud agreements buy only capacity that is unsold. A new law, a late building or a weak quarter does not flip all of them on at once.

The figure below shows NVIDIA's promises by fiscal year, and which ones pay only on default.

NVIDIA's promises by fiscal year, $ billionsStacked bars: scheduled commitments from the 10-Q for the quarter ended 26 Jul 2026, by NVIDIA fiscal year. Boxes at right: guarantees that pay only if a tenant defaults, so they sit on no schedule.NVIDIA's promises by fiscal year, $ billionsStacked bars: scheduled commitments from the 10-Q for the quarter ended 26 Jul 2026, by NVIDIA fiscal year.Boxes at right: guarantees that pay only if a tenant defaults, so they sit on no schedule.$0B$30B$60B$90B$120BFY2027 rest: Supply and capacity (memory $92BFY2027 rest: Cloud for NVIDIA's own research $3BFY2027 rest: Equity investments still to be made $18B$113BFY2027 restFY2028: Supply and capacity (memory $87BFY2028: AI cloud agreements: buy back of hours from clouds that bought NVIDIA gear $6BFY2028: Cloud for NVIDIA's own research $8BFY2028: Equity investments still to be made $3BFY2028: Leases for NVIDIA's own use $1B$105BFY2028FY2029: Supply and capacity (memory $88BFY2029: AI cloud agreements: buy back of hours from clouds that bought NVIDIA gear $8BFY2029: Cloud for NVIDIA's own research $7BFY2029: Equity investments still to be made $2BFY2029: Leases to hand to third parties $1BFY2029: Leases for NVIDIA's own use $1B$107BFY2029FY2030: Supply and capacity (memory $6BFY2030: AI cloud agreements: buy back of hours from clouds that bought NVIDIA gear $7BFY2030: Cloud for NVIDIA's own research $6BFY2030: Equity investments still to be made $2BFY2030: Leases to hand to third parties $1BFY2030: Leases for NVIDIA's own use $2B$24BFY2030FY2031: Supply and capacity (memory $5BFY2031: AI cloud agreements: buy back of hours from clouds that bought NVIDIA gear $6BFY2031: Cloud for NVIDIA's own research $4BFY2031: Leases to hand to third parties $1BFY2031: Leases for NVIDIA's own use $1B$17BFY2031FY2032+: Supply and capacity (memory $1BFY2032+: AI cloud agreements: buy back of hours from clouds that bought NVIDIA gear $9BFY2032+: Cloud for NVIDIA's own research $1BFY2032+: Leases to hand to third parties $17BFY2032+: Leases for NVIDIA's own use $20B$48BFY2032+Pays only on default:Ohio leases, OpenAI tenantcap $105B; per phase from FY2029AI cloud lease guaranteescap $3.5B; $712M in escrow$500B financing platformsmemoranda only, not signedSupply and capacity $279BAI cloud buy backs $36BOwn research cloud $29BEquity still to invest $25BLeases for third parties $20BOwn use leases $25BSource: NVIDIA 10-Q, quarter ended 26 Jul 2026, Note 10 and MD&A; 8-K of 17 Aug 2026. Fiscal 2029 starts late Jan 2028.
Figure 6. NVIDIA's commitments by fiscal year from its 10-Q for the quarter ended 26 July 2026. The $279 billion of supplier promises falls almost entirely by fiscal 2029; the $36 billion of compute buy backs from AI clouds starts in fiscal 2028; the Ohio guarantees (capped at $105 billion) and the cloud lease guarantees (capped at $3.5 billion) sit outside the schedule because they pay only if a tenant defaults, and the Ohio ones start only as each phase is ready for service from calendar 2028. Source: NVIDIA 10-Q and 17 August 2026 8-K.
Table view: NVIDIA commitments by fiscal year ($B)
Fiscal yearSupply and capacityAI cloud agreementsOwn research cloudEquity to investLeases for third partiesOwn leases
FY2027 rest92031800
FY20288768301
FY20298887211
FY2030676212
FY2031564011
FY2032+19101720

What financing cannot do

It cannot turn a forecast into a bill. It cannot make a chip in a crate earn rent. It cannot put the same dollar to work twice. Once the loan has bought the rack, the cash is inside a controlled account, and the owner cannot park it in Treasury bills or in the stock market.

Even if it could, the arithmetic would not help. On 26 October 2026 Treasury bills paid 4.11 to 4.35 percent for one to six months (US Treasury). The S&P 500's trailing earnings yield, meaning the last year's profits divided by the price, was 3.82 percent, and its dividend yield was 1.06 percent (multpl earnings yield; multpl dividend yield). The chip loans cost 6 to 10 percent. Borrowing at those rates to hold the index loses money as a yield, and the index is full of the same AI bet as the chips. For scale, a single A company bond paid 0.76 percent over Treasuries on 23 October 2026 (ICE BofA single A index via FRED), so the contractual spread on an A3 rated chip loan, 2.25 points over SOFR, is about three times the spread an ordinary A rated company bond pays over Treasuries; the two bases differ, so that is a rough comparison, not an exact one.

The players

Who What they own How they get paid What breaks them
NVIDIA (layer two: chips) Chip designs, the software, a place in line at the factories, $99 billion of stakes in other companies Cash shortly after delivery, 75 percent gross margin Customers stop ordering. A large but undisclosed share of $279 billion of supplier promises stays due. Guarantees pay out if live projects fail or if Ohio opens from 2028 and OpenAI then misses rent.
ASML, TSMC, SK hynix, Samsung, Micron, substrate, packaging and test firms (layer two: chips) The ability to make the chip NVIDIA's orders and, now, NVIDIA's advances and customer cash deposits NVIDIA cuts orders, or their own factories slip.
Utilities, ERCOT, PJM, turbine and transformer makers (layer one: energy) The right to connect, and the gear Rates, connection fees, equipment sales Politics, queues, lead times. They are the bottleneck. They are not the ones borrowing against chips.
Building landlords (layer three: infrastructure) Halls and power contracts About $1 billion to $2 billion a year per gigawatt of shell A tenant with no chips, or a grid that will not connect the next hall.
Microsoft, Google, Amazon, Meta, Oracle (layer three: infrastructure, paid by their own layer five businesses) Whole companies, plus their own sites Ads, cloud, retail, software. The site is inside that. The product never earns the hurdle. The company still pays its bonds. Meta's off balance sheet ventures carry $41.5 billion of residual value guarantees.
OpenAI, Anthropic, and other labs (layer four: models) The model and the customer relationship Subscriptions and API bills They signed long rents and the price of tokens fell. They still owe the rent.
Enterprises and consumers (layer five: applications) The reason anyone pays They are the payers, through subscriptions and token bills The answers stop being worth the price, and the revenue every layer below waits on does not arrive.
SpaceX (layer three as a cluster landlord; layer four through SpaceX.AI) Starlink, launch, and the SpaceX.AI clusters Those businesses, plus short term chip rent Customers leave in 90 days while the Apollo lease runs five years, on top of $39 billion of existing debt. Other income is what keeps that from being fatal.
CoreWeave, Nebius, Lambda, IREN, Crusoe, Nscale, and the smaller neoclouds (layer three: infrastructure) Chips, a lease, and a customer contract The customer's bill, minus power, interest and operating cost The contract ends, the site is late, or nobody will sign the next one. CoreWeave pays about a quarter of revenue in interest; its default insurance traded above 1,000 basis points in October 2026.
Apollo, Blackstone, Blue Owl, banks, insurers, private credit funds (lenders to every layer) The loan, the lease, or the chips if the borrower fails Interest and principal The contract was shorter than the loan, or the building never turned on.
The buyer of a 90 day rental (layer four or five) Nothing physical They pay the high price and can leave The price rises and the owner kicks them off to rent again.

Who sets the date, what regulation does, what a ban would do

Who sets the date

NVIDIA's ship date is the date the industry is organized around. NVIDIA is paid then. An unsold rack is NVIDIA's cash sitting still. Buyers who pass can lose the generation, or lose the customer who wanted that generation.

NVIDIA pulls the rest of the chain toward that date. Buyers order before the hall is done. Lenders are asked to fund chips that cannot yet be turned on. The prefabricated pod shortens the weeks after a ready site exists. When a buyer still cannot pay, NVIDIA agrees to buy unused hours or stand behind a lease, so the shipment still happens. NVIDIA's own filing names the risk: "Customers may postpone purchasing new architectures due to the lack of availability of data center infrastructure to deploy our products, constraints on capital to have sufficient funding to purchase our products" (NVIDIA 10-Q).

NVIDIA does not control the hookup. A buyer with other income can refuse a bad delivery or rent the chips out for 90 days. A buyer whose only business is those chips takes the shipment, because losing the allocation feels worse than paying for idle hardware.

What regulation does

Rules do not create the shortage. They write down who gets the hookups that remain.

Texas paused new data center connections by directive while it audits the queue, as section 3 described. PJM's board tried something larger. A board letter instructs PJM's staff to develop rules and file them with FERC; it changes nothing on its own. On 16 January 2026 the board called for a voluntary "Bring Your Own New Generation" path with an expedited interconnection track for the new power plant, and a "connect and manage" regime under which new large loads that do not bring generation would be curtailed before ordinary emergency measures (PJM Board letter, 16 January 2026). On 27 July 2026 it set the details: a one time backstop auction targeting about 6.8 gigawatts with 15 year commitments, and an "Interim Resource Adequacy Service" under which new large loads that do not bring their own new supply by 1 June 2027 would be cut first when the system nears an emergency. The letter's principle: "Existing consumers should not bear higher capacity costs caused by new Large Loads that do not bring, or otherwise contract for, the new supply necessary to serve them" (PJM Board letter, 27 July 2026; Utility Dive, 28 July 2026).

The seed of this report cited a PJM board letter of October 2026. There is none. What happened in the autumn was the federal regulator acting on the summer letter. On 29 September 2026 FERC accepted the backstop auction filing but suspended it to 28 February 2027, with Chair Laura Swett saying the commission "will not be forced into accepting a deeply flawed, eleventh-hour procurement mechanism with billion-dollar implications for consumers" (FERC order, docket ER26-3380; Utility Dive). On 9 October 2026, in a second order, FERC rejected the curtailment service and the bring your own capacity rules, finding that they would place obligations on retail customers and decide which retail customers are curtailed, matters that belong to the states, and accepted only PJM's large load definition and registry (FERC order, docket ER26-3515; Utility Dive, 12 October 2026). So as of 27 October 2026, PJM's fast track and curtailment regime, as filed, is not in force. The board wants it. The federal regulator blocked the curtailment half and sent the question of who gets cut first to the states.

The direction of travel still shows. On 4 March 2026 Amazon, Google, Meta, Microsoft, OpenAI, Oracle and xAI signed the White House's Ratepayer Protection Pledge to supply their own new generation, pay for grid upgrades and accept separate rate structures (White House, 4 March 2026). No neocloud signed. A hyperscaler or SpaceX can fund a plant. A small landlord usually cannot.

Who pays in the meantime shows up in PJM's capacity market. Once a year PJM pays power plants to promise to be available in a future year, and every customer in the region pays a share through their bill. The price is quoted per megawatt per day. It was $28.92 for the 2024/25 delivery year, $269.92 for 2025/26, then $329.17, $333.44 and $325.00 for the next three years, each at the price cap, an eleven fold rise in four years; $325 per megawatt per day is $325 × 365 = $118,625 per megawatt a year, or about $10 per kilowatt per month, beside shell rent of about $150 per kilowatt per month. The last two auctions cleared short of the reliability requirement by 6,516.6 and 6,831.3 megawatts (PJM 2027/28 report; PJM 2028/29 report). PJM's market monitor attributes $29.4 billion of the $63.6 billion of capacity cost across the last four auctions to data center load, or 29.4 ÷ 63.6 = 46 percent, as reported by Utility Dive (Utility Dive, 20 July 2026).

The figure below shows the capacity price by delivery year and the share the market monitor attributes to data centers.

PJM capacity price by delivery year, $ per megawatt per dayWhat power plants are paid to promise availability in the grid region covering Virginia, Pennsylvania and Ohio. $28.92 for 2024/25, $269.92 for 2025/26, then the cap; the last two auctions fell short of the requirement.PJM capacity price by delivery year, $ per megawatt per dayWhat power plants are paid to promise availability in the grid region covering Virginia, Pennsylvania andOhio. $28.92 for 2024/25, $269.92 for 2025/26, then the cap; the last two auctions fell short of the$0$100$200$3002015/16: $136/MW-day, total cost $9.7B15/162016/17: $59.37/MW-day, total cost $5.5B16/172017/18: $120/MW-day, total cost $7.5B17/182018/19: $164.77/MW-day, total cost $10.9B18/192019/20: $100/MW-day, total cost $7B19/202020/21: $76.53/MW-day, total cost $7B20/212021/22: $140/MW-day, total cost $9.3B21/222022/23: $50/MW-day, total cost $3.9B22/232023/24: $34.13/MW-day, total cost $2.2B23/242024/25: $28.92/MW-day, total cost $2.2B24/252025/26: $269.92/MW-day, total cost $14.7B25/26$269.922026/27: $329.17/MW-day, total cost $16.1B26/27$329.172027/28: $333.44/MW-day, total cost $16.4B, 6516.6 MW short of the reliability requirement27/28$333.442028/29: $325/MW-day, total cost $16.4B, 6831.3 MW short of the reliability requirement28/29$325Market monitor: data centers caused $29.4B of the $63.6B (46%)of capacity charges over the last four auctionsSources: PJM Base Residual Auction reports (2025/26, 2027/28, 2028/29). Market monitor attribution: Utility Dive, 20 Jul 2026 (secondary). Hover a bar.
Figure 7. PJM's capacity auction clearing price by delivery year. The price rose from $28.92 per megawatt day for 2024/25 to $269.92 for 2025/26 and then cleared at the cap (about $325 to $333) for the next three years, with the 2027/28 and 2028/29 auctions short of the reliability requirement by 6,517 and 6,831 megawatts. The market monitor attributes $29.4 billion of the $63.6 billion of capacity charges over the last four auctions to data center load. Sources: PJM auction reports; Monitoring Analytics via Utility Dive.
Table view: PJM capacity auction results
Delivery yearPrice ($/MW-day)Total cost ($B)Short of requirement (MW)
2015/161369.7
2016/1759.375.5
2017/181207.5
2018/19164.7710.9
2019/201007
2020/2176.537
2021/221409.3
2022/23503.9
2023/2434.132.2
2024/2528.922.2
2025/26269.9214.7
2026/27329.1716.1
2027/28333.4416.46516.6
2028/2932516.46831.3

The states are writing their own terms. Ohio's 85 percent minimum bill cut AEP's queue from 30 gigawatts to 5.6 gigawatts of signed agreements, as section 3 showed. Virginia's regulator created a new rate class for customers of 25 megawatts and up, effective 1 January 2027, with an 85 percent minimum transmission charge (SELC, 25 November 2025). Texas Senate Bill 6 covers loads of 75 megawatts and up and requires equipment so they can be cut during rolling blackouts (Utility Dive on SB 6). Third party trackers count 32 Indiana counties and 20 of North Carolina's 100 with moratoriums on new data centers (Electric Choice tracker; datacenterbans.com); the counts disagree between trackers. A federal bill, S. 4214, would impose a nationwide moratorium on building or upgrading data centers of 20 megawatts or more; it has had no action since introduction (Congress.gov). Abroad, Ireland's data centers used 22 percent of the country's metered electricity in 2024 (CSO Ireland), and since December 2025 a new data center there must bring its own dispatchable generation or storage sized to match its maximum draw (A&L Goodbody on the CRU decision).

NVIDIA is upstream of all of this. It has already been paid for chips that may sit dark. Later orders shrink if fewer sites are allowed to turn on. The hyperscalers stay at the front of the line, because they can meet a "bring your own power" test and still sign contracts lenders trust. Everyone after them rents whatever power is left.

If new data centers were banned

A ban on new halls ends the growth story. It does not turn off halls that are already running. Every measure found for this report, from the Texas audit to the county moratoria to the Senate bill to Ireland's rule, targets new connections or new permits, not live sites. The Senate bill also covers upgrades of existing sites of 20 megawatts or more.

New chip sales flatten to whatever fits inside power that already exists. That is far below the path NVIDIA's supplier promises assume. NVIDIA still owes a large but undisclosed share of those bills.

Chips already running get scarcer, so their rent and resale value go up. The 2026 data shows the direction even without a ban: the main H100 rental index rose from $2.00 per GPU hour on 9 December 2025 to about $2.88 on 24 October 2026, about 44 percent, by secondary readings of the index, while new capacity was still being built (Silicon Data index page); that is a scarcity rent during a buildout, not evidence of what a ban would do. Chips in crates, headed for a building that cannot be finished, have nowhere to go. Loans against that second pile break. The customer can walk. The debt remains. There is no bill.

The guarantees do not all come due on the day a ban passes.

A ban is existential for the buildout, for lenders behind unfinished sites, and for a neocloud whose plan was to keep opening halls. It is a shrink to fit for companies that already own live power.

What earlier buildouts teach

A buildout is a period when many companies race to build the same kind of long lived equipment at once because they all believe demand will be huge. The seed of this report asks five things of each one: who was paid at delivery, who carried the long bill, who held the demand risk, what the scarce input was, and what broke. The pattern across every episode below is that the sellers of physical inputs were paid at or near delivery, and the losses landed on whoever lent long against a forecast of demand that arrived later or smaller than expected. The asset usually survived and was run by a new owner who bought it cheaply. The exception is equipment that goes obsolete fast, where the asset itself lost most of its value.

Railroads

Railroads were built mainly with borrowed money, much of it from London, in waves that each ended in a crisis (Giesecke, Longstaff, Schaefer and Strebulaev, NBER Working Paper 15848). The corporate bond market of the time was mostly railroad bonds, and the railroad crashes are the worst bond default episodes in US history: default rates summed to 35.90 percent of the par value of the whole US corporate bond market over 1873 to 1875, and 18.69 percent over 1892 to 1894, against 12.88 percent in the worst three years of the Great Depression (same paper). A bond is a loan sold to investors in pieces, and par is the amount promised back. A default is a missed payment.

What happened next is the useful part. Receivership was the court process in which a judge appointed a receiver to keep running the trains while the lenders worked out who took the loss; the modern version is Chapter 11. Mileage operated by receivers was 40,819 miles in 1894 (Historical Statistics of the United States, Table Df964) out of 178,709 miles of road (US Census, Historical Statistics 1789 to 1945, chapter K), which I compute as 40,819 ÷ 178,709 = 22.8 percent of the country's track under court control in one year. The judge in the 1884 Wabash case put the logic in one line: without money to keep it running, "you have nothing else but a streak of iron-rust on the prairie" (quoted in the NBER paper). The trains kept running. Old high interest bonds were swapped for new bonds at lower rates (Daggett, Railroad Reorganization, 1908). The asset kept its value as a going railroad because the traffic continued and the right of way had no rival. The bondholders took the cut.

Electrification

Electricity came with a different financing problem: holding company pyramids. Samuel Insull's companies were stacked "sometimes ten layers thick," and by the late 1920s the 16 largest holding companies controlled more than 75 percent of US generation (EIA, The Changing Structure of the Electric Power Industry, DOE/EIA-0562(96)). Insull's top companies went into receivership in 1932. Congress passed the Public Utility Holding Company Act in 1935 to break the pyramids up, and by 1950 the reorganizations were "virtually complete" (same source). The operating plants and wires kept running under state commissions that set prices to give the utility "a fair rate of return." That deal, one network per territory and a regulated return, is what the electricity era left behind. It is why state commissions still set retail rates and decide who may build wires, while a large site in Texas or PJM buys its energy in a wholesale market run by the grid operator.

Telecom and fiber

The 1990s fiber buildout is the closest match on financing. US carrier capital spending rose from $42.5 billion in 1996 to $113.1 billion in 2000, then fell to $92.6 billion in 2001, per a Credit Suisse First Boston series cited in an industry filing to the FCC, which blamed "subsequently discredited claims that Internet traffic was doubling every three months (instead of every 9-12)" (TIA filing to the FCC, 13 November 2002).

Vendor financing is when the company selling the equipment also lends the buyer the money to pay for it. Lucent's own annual report shows the result. Its customer financing commitments, loans plus guarantees, were $8.1 billion at 30 September 2000. A year later it "recorded provisions for uncollectibles and customer financings of $2.2 billion ... of which approximately $1.3 billion was related to three customer finance projects, including Winstar and One.Tel" (Lucent 10-K405, fiscal 2001). The seller booked the sale, then ate the loan. That is the same shape as a chip seller standing behind its buyers' leases.

When the carriers failed, their lenders did badly. Moody's found that the average recovery on defaulted telecom bonds was 23.2 percent over 1982 to 2003, the lowest of any industry it tracked (Moody's, Default and Recovery Rates 1920 to 2003). A recovery rate is the share of a loan the lender eventually gets back. Global Crossing "reportedly spent $13.7 billion" building 100,000 miles of cable (House Financial Services Committee, March 2002) and emerged from bankruptcy with ST Telemedia holding 61.5 percent for $250 million of new money, per trade press (Global Custodian). Control of a network that cost $13.7 billion passed for $250 million of new money, with the creditors keeping the rest.

The famous line that only 2.7 percent of the fiber was ever lit is a misquote. Lit fiber has equipment at each end; dark fiber is glass in the ground carrying nothing. TeleGeography found that of long haul fiber passing through Chicago in 2002, 3.9 percent was lit, and that 2.7 percent of that lit capacity carried internet traffic (Network World, 8 September 2003). The glass was not wasted in the end: capacity per strand rose from about 2.5 gigabits a second in 1996 to 100 gigabits later as the equipment at the ends improved (Federal Reserve Bank of Richmond, Fall 2003). The glass gained value. The end equipment, and the companies that lent against the forecast, lost.

The data center landlords of 2001

Exodus Communications was one of the largest data center landlords of the first Internet boom and filed for bankruptcy on 26 September 2001 when its dot com tenants vanished. Cable & Wireless bought 26 of its 44 operating data centers for about $575 million in cash plus about $180 million of liabilities (Computerworld), and the buildings were later leased or bought by Savvis, Google and others (Data Center Knowledge). Equinix survived the same winter by retiring about $169.6 million of its notes for about $17.7 million of cash plus about 2.4 million shares, about 10 cents of cash per dollar of face (Equinix 10-K, fiscal 2002); the retired amount and the cents per dollar are my arithmetic on the filing's figures. The buildings survived. The landlord's bondholders did not get paid in full.

Shale and reserve lending

Oil drillers borrow against the estimated value of oil still in the ground. The Dallas Fed describes the method: traditional reserve based loans advance 40 to 50 percent of asset value, and lenders recompute the limit twice a year at current prices (Dallas Fed, 15 October 2026). When oil fell in 2014 to 2016, producer bankruptcies peaked at 70 filings and $56.8 billion of debt in 2016 (Haynes and Boone). The lesson for chips is the advance rate: a lender that advances half of a volatile asset's value survives a halving. One that advances 90 percent does not, unless a signed contract, not the asset, is what it is really lending against.

Bitcoin mining

Bitcoin mining is the nearest precedent for loans backed by chips. An ASIC is a chip built for a single job, in this case bitcoin's hash function, so its resale value tracks mining profitability almost directly. From 7 May 2021 to 25 December 2022 the price per unit of mining power fell 86.82 percent for the most efficient machines and 91 percent for the least efficient, per Hashrate Index data (FXStreet on Hashrate Index; Hashrate Index). Lenders had advanced 75 to 80 percent of the machines' value, per a former insider quoted by Bloomberg (DSHR blog), on an estimated $2 billion to $4 billion of such loans (Hashrate Index).

Then the lenders took the machines. Stronghold returned about 26,200 miners to its lenders to extinguish $67.4 million of debt (Stronghold 8-K). Core Scientific handed 27,403 rigs to NYDIG to extinguish $38.6 million, arguing the debt exceeded the collateral's value (CoinDesk). Two Iris Energy subsidiaries defaulted on about $104 million of equipment loans that were non recourse, meaning the lender could take only the machines and not the parent's other assets (Iris Energy 6-K, 21 November 2022). The sites and the power contracts stayed with the miners, and those turned out to be the valuable part: Iris Energy is now IREN with a $9.7 billion Microsoft contract and TeraWulf and Cipher rent to Fluidstack under Google backstops, as section 6 showed; Core Scientific hosts CoreWeave (Core Scientific S-1, 2024) and Hut 8 sold $3.25 billion of notes against a 15 year Fluidstack lease (Hut 8 8-K, April 2026). The chips were worth almost nothing within 19 months, and the power contracts were worth a new business.

What maps and what does not

Chips are closer to mining ASICs than to fiber or track. Track and glass lasted decades and gained value as the equipment at the ends improved. A GPU is written off over three to six years and can lose resale value when the next generation arrives. The mining collapse is the path to fear, not a result this report has shown for GPUs: H100 rents rose through 2026 and NVIDIA says 2020 chips are still busy. The lender's protection is the signed contract, not the chip.

The biggest buyers today have other income, which the fiber builders did not. Global Crossing and Exodus had nothing to carry them through a slump. Microsoft, Alphabet, Amazon and Meta carry large profits from other businesses and borrow as themselves, so a slowdown hits them through lower returns, not default. The neoclouds and former miners that rent to labs are closer to Exodus and Global Crossing: one business, borrowed money, a few tenants.

Take or pay contracts and guarantees move the demand risk to the signer. Railroads had no take or pay contracts with shippers. Many AI leases do, and some have a hyperscaler or NVIDIA behind them, so the loss lands on the guarantor rather than on the landlord's bondholders. Vendor financing, Lucent's version and NVIDIA's, moves it back toward the seller.

On size, Torsten Slok of Apollo puts hyperscaler capital spending at 1.4 percent of US GDP in 2025, against telecom's peak of 1.2 percent in 2000 and housing's 6.6 percent in 2005, with consensus forecasts near 3 percent by 2027 (Apollo Daily Spark, 6 August 2026). A widely repeated figure of 6 percent for railroads in the 1880s rests on secondary sources and was not verified for this report (Investment Research Partners chart).

How to read a new headline

Ask four questions. Each one below is worked through with the SpaceX and Google deal from section 5.

  1. Which price is this: NVIDIA's sales into a site, the owner's rent, or the return a builder needs? In 2026 the four prices sat at about $25 billion to $40 billion of NVIDIA gear per gigawatt (a one time cost), $40 billion to $50 billion a year of short rent, about $9.7 billion a year in the one public multi year contract, and about $11.6 billion a year of revenue a builder needs. Google's $920 million a month is rent, and at roughly $50 billion to $60 billion per gigawatt year it is the scarcity price, not the price a builder would plan on. Huang's "$40 billion a year" in Berlin is also rent, quoted as if it were a return.
  2. Who has promised to pay, and can they leave? A take or pay and a 90 day deal are not the same asset. Google can leave on 90 days' notice after 31 December 2026, so the firm commitment is $5.52 billion, not the $30.4 billion of the full term. Meta's contract with CoreWeave is take or pay, which is why the loan against it is rated A3.
  3. Is the power already connected? A chip without a hookup earns nothing. A chip in a live hall is the scarce one. Google's deal had a delivery date, 30 September 2026, with the right to leave or pay less if the chips were not live by then; no later filing read for this report says whether SpaceX met it.
  4. Does the guarantee start now, or only after a building is finished and a tenant then misses a payment? The Google deal has no guarantee; SpaceX's own income is what stands behind the Apollo lease. NVIDIA's Ohio guarantees start only as each phase is ready for service from 2028, and pay only if OpenAI then defaults.

If the headline skips these, it is mixing a speech, a loan, and a wish.

The conjecture, and what would break it

The conjecture

The scarce input sets the date, and today that is power. Chips arrive in months, buildings and hookups in years, and the queue in Texas alone holds five times the state's record demand. NVIDIA still ships on its own date because losing a place in line costs a buyer more than idle hardware does.

The only durable demand is a signature from a buyer with other income. A take or pay contract from Microsoft or Meta is collateral; a 90 day deal is rent; a letter of intent is a wish. Financing prices the signature, not the chip, which is why the same racks borrow at SOFR plus 2.25 percent behind Meta and SOFR plus 5.50 percent behind three year contracts.

Most of NVIDIA's promises pay only on default or on unsold live hours. The $36 billion of cloud agreements buys capacity nobody else rented, with nothing due before fiscal 2028. The Ohio guarantees start as buildings open from 2028 and pay the shortfall only if OpenAI misses rent. The supplier commitments of $279 billion are the one line that runs the other way, and a large but undisclosed share of them is fixed.

A ban or a demand shock lands first on unfinished sites and single business landlords, and on the lenders behind them. Live halls with signed tenants keep paying, and their chips get more valuable, not less.

What would break this argument

Power could stop being the constraint. Prefabricated pods plus gas turbines on site would move the clock from the grid operator to the turbine maker; BloombergNEF counts 74 gigawatts of announced on site gas at US data centers, per Utility Dive (Utility Dive, 29 September 2026). If that capacity arrives, chips become the bottleneck again, and the HBM shortage the IEA expects through 2027 would set the date instead.

The price of a fixed level of ability could keep falling 13 times a year while token volume grows slower than that. Then spending falls even as use rises. Ramp's latest month shows the opposite, prices down 25 percent and token spending up 23 percent, so the month to watch is the first in which those two lines cross. If that becomes a year, the $800 billion of 2026 capex is building against a shrinking bill, and the long contracts the labs signed "regardless of actual usage" become the problem rather than the solution.

A lab could fail to refinance. OpenAI's reported losses and burn are press figures, but the Ohio guarantee is the test case written into a filing: if OpenAI cannot pay rent on a building NVIDIA guaranteed, the circular piece stops being a footnote.

NVIDIA's cancelable share of the $279 billion could turn out to be small. Then a demand pause lands on NVIDIA as a Lucent style provision rather than a $4.5 billion H20 style charge, and the company that is paid at delivery becomes the company holding the inventory.

The giants' off balance sheet leases could come back. Moody's counted $662 billion of leases signed but not yet started, and Meta's ventures carry $41.5 billion of residual value guarantees that it books as "not probable." In a downturn, a four year lease that was meant to be renewed to 20 is either renewed at a loss or walked away from with a guarantee payment, and either way the debt that was not on the balance sheet lands on the earnings.

States, not FERC, now decide who gets cut first in an emergency, and they could choose households over data centers. A state that puts homes first turns a firm hookup into an interruptible one, and a lender that priced a loan on firm power would reprice it.

None of these has shown up yet as a default, a cancelled order or a written down lease; the exposures and the warnings are already in the filings. The ones to watch are the share of the $279 billion that is firm, the first draw on the $36 billion line in fiscal 2028, the ready for service date of the first Ohio phase, and the first month in which Ramp's token spending falls while its price per token keeps falling.

Data sources and methodology

Research date: 27 October 2026. SK hynix and GE Vernova reported third quarter results on 28 October 2026; the memory and gas turbine passages were rechecked against those releases on 1 November 2026, and the rest of the report stands as of 27 October. The research was done in seven slices (compute first principles, the chip supply chain, power and buildings, demand and pricing, financing, regulation and risks, history), each checked against the primary documents by three independent audit passes before the prose was written from the author's seed document of 27 October 2026 and the research files. Every numeric series used for the figures is kept in a data table with a source column, available on request.

Primary documents. NVIDIA Form 10-Q for the quarter ended 26 July 2026 (link), Form 8-K of 17 August 2026 on the SB Energy guarantees (link), Form 10-K for fiscal 2026 (link), CFO commentary for Q2 FY2027 (link), the Q2 FY2027 earnings call (transcript), and NVIDIA's releases of 10 August and 21 October 2026. CoreWeave Forms 8-K of 9 September 2025, 30 September 2025, 31 March 2026, 15 May 2026, 10 August 2026 and 17 September 2026 with their exhibits, the 10-Q for the quarter ended 30 June 2026 and the 2025 S-1. SpaceX free writing prospectus of 5 June 2026, 8-K of 26 October 2026 and 10-Q for the quarter ended 30 September 2026. Anthropic S-1, accession 0001628280-26-067168, filed 26 October 2026. Meta 10-Q for the quarter ended 30 September 2026 and Q3 2026 release. Microsoft, Alphabet, Amazon and Oracle earnings releases, transcripts and 10-Q and 10-K filings. AMD 8-Ks of 6 October 2025 and 24 February 2026 and 10-Q for the quarter ended 27 June 2026. Broadcom 8-K of 6 April 2026 and Q3 FY2026 release. TSMC, ASML, Micron, SK hynix, Foxconn, Supermicro and Dell quarterly releases. IREN 10-K for fiscal 2026, Nscale S-1, Lambda's release, TeraWulf and Cipher 8-Ks. Applied Digital 8-K of 29 August 2025. PJM Board letters of 16 January and 27 July 2026, PJM base residual auction reports for 2025/26 through 2028/29, FERC orders in dockets ER26-3380 (29 September 2026) and ER26-3515 (9 October 2026). ERCOT Senate deck of 29 July 2026 and board deck of 13 April 2026, and the Texas governor's directive letter of 3 August 2026. CBRE North America Data Center Trends H1 2026. EIA Electric Power Monthly and residential consumption data. US Treasury yield curve, New York Fed SOFR, ICE BofA spreads via FRED, multpl. NBER Working Paper 15848, Historical Statistics of the United States, EIA DOE/EIA-0562(96), the TIA filing to the FCC of November 2002, Lucent 10-K405 for fiscal 2001, Moody's default study of January 2004, Equinix 10-K for 2002, Haynes and Boone, the Dallas Fed banking note of 15 October 2026, Stronghold and Iris Energy filings, Hashrate Index. Artificial Analysis leaderboard and Epoch AI data and publications. Apple, Google, Moonshot and Qwen release pages. Jensen Huang, "AI Is a 5-Layer Cake," NVIDIA blog, 10 March 2026 (link). The five layer frame is Huang's; the clocks, the prices and the order in which each layer pays the next are this report's reading of the filings.

Load bearing numbers that are secondary. Goldman Sachs's per gigawatt figures ($40 billion to $50 billion short rent, "around 20 billion" long contract, $11.6 billion hurdle on $42 billion of build cost, the May 2026 delay estimate) come from a Yahoo Finance video and two writeups; the notes are not public. CBRE's $165 per kilowatt per month is a third party reading of CBRE's charts; CBRE's text gives only percent changes. The Meta Hyperion bond terms, Oracle's and CoreWeave's credit default swap levels, OpenAI's revenue and loss figures, the $300 billion Oracle and OpenAI contract, the NVIDIA investment of $30 billion in OpenAI, and the H100 rent index history are press reports. Rack prices ($3 million for GB200 NVL72, $7.8 million for Vera Rubin NVL72) are analyst and press figures; NVIDIA publishes none. Huang's chip life of "seven or eight years" is a reporter's paraphrase, not a quote. The Dominion seven year wait is one article. The Texas audit completion date of 10 December 2026 is a law firm note. Company server useful lives are quoted from secondary summaries of the 10-K filings where this report lacked a direct link. The 6 percent of GDP figure for railroads is secondary and unverified.

Not claimed because not found. A measured training versus inference split at any company. TSMC's CoWoS capacity in wafers. A lender's written GPU life assumption other than the six years in CoreWeave's August 2026 credit agreement. A rated pure GPU asset backed security. An A100 resale price series. The share of planned capacity held by neoclouds. A measured 2026 cut in enterprise AI spending. The CNBC summary of NVIDIA's filing cited in the seed. A Reuters report on the Apollo lease. The original Goldman Sachs notes.

Arithmetic. Every worked figure (homes per gigawatt, racks per gigawatt, cost per answer, rent per gigawatt, electricity per gigawatt year, the SpaceX and Google per hour and per gigawatt prices, the locked share of each 90 day deal, IREN's per gigawatt rate, the capex sum, the loan rate gap, the Apollo repayment schedule, the receivership share, Equinix's cents per dollar) is this report's own division or multiplication of sourced inputs, and the inputs are linked where each one appears.